GON - Studied
S No | Project | Capacity (MW) | River | Latitiude N | Longitude E | VDC/District | Remarks | ||
---|---|---|---|---|---|---|---|---|---|
1 | Bheri Khola | 5.000 | Bheri Khola | 29o 07' 53" | 29o 13' 07" | 81o 55' 58" | 82o 05' 18" | Tamti (Jumla) | changed status to GON- Basket on COD : 2076-10-12 |
2 | Bheri-Babai Diversion Project | 48.000 | Bheri | 28o 20' 10" | 28o 29' 45" | 81o 18' 50" | 81o 52' 26" | BirendraNagar N.P. (Surkhet) | Under construction by Dept of Irrigation |
3 | Budhi Gandaki Storage Hydropower Project | 1200.000 | Budhi Gandaki | 27o 48' 30" | 28o 07' 30" | 84o 42' 30" | 84o 56' 00" | Budhathum,Chainpur,Khari,Maidi,Salyantar,Salang (Dhading) Namjung,Dhawa,Darbhung,Borlang,Ghyalchok,Tandrang (Gorkha) | detailed engineering study completed 2072/73 |
4 | Dotigad | 2.520 | Doti Gad | 29o 17' 37" | 29o 18' 20" | 80o 29' 06" | 80o 30' 30" | Bagarkot (Dadeldhura) | changed status to GON- Basket on COD : 2074-08-25 |
5 | Dudh Koshi-IV | 47.000 | Dudh Koshi | 27o 27' 00" | 27o 29' 46" | 86o 41' 00" | 86o 44' 20" | (Solukhumbu) | changed status to GON- Basket on COD : 2076-03-23 |
6 | Jawa Khola | 17.550 | Jawa Khola | 29o 16' 26" | 29o 19' 01" | 82o 12' 21" | 82o 15' 50" | Chhumchaur,Chandan Nath,Dillichaur,Garjyangkot,Patmara,Patarasi (Jumla) | changed status to GON- Basket on COD : 2075-12-28 |
7 | Kawadi Khola | 30.000 | Kawadi Khola | 29o 45' 00" | 29o 48' 18" | 81o 43' 00" | 81o 45' 00" | Maila (Humla) | changed status to GON- Basket on COD : 2077-03-30 |
8 | Loti Karnali (Darma) | 49.500 | Darma Khola | 29o 44' 30" | 29o 49' 13" | 82o 03' 18" | 82o 05' 36" | Mimi (Humla) | changed status to GON- Basket on COD : 2078-03-31 |
9 | Lower Chepe Khola HPP | 8.740 | Chepe Khola | 28o 08' 11" | 28o 10' 30" | 84o 34' 30" | 84o 37' 19" | Chiti (Lamjung) | changed status to GON- Basket on COD : 2074-08-25 |
10 | Lungri Khola | 4.400 | Lungri | 28o 14' 52" | 28o 18' 30" | 82o 43' 00" | 82o 47' 45" | Harjang (Rolpa) | (i) changed status to GON- Basket on COD : 2076-05-29 (i) Project boundary amended from 281400 to 281452 in south, Decision Date: 2079-04-10 |
11 | Maiwa Khola | 12.504 | Maiwa | 27o 21' 00" | 27o 22' 37" | 87o 33' 58" | 87o 37' 37" | (Taplejung) | changed status to GON- Basket on COD : 2074-08-25 |
12 | Mustang Wind Power | 0.450 | 00o 00' 00" | 00o 00' 00" | 00o 00' 00" | 00o 00' 00" | Jomosom (Mustang) | ||
13 | Myagdi Khola | 15.200 | Myagdi Khola | 28o 18' 45" | 28o 22' 00" | 83o 30' 00" | 83o 35' 30" | Devisthan (Myagdi) | changed status to GON- Basket on COD : 2077-03-30 |
14 | Nyaurigad | 4.015 | Nyauri Gad | 29o 23' 00" | 29o 24' 30" | 82o 08' 30" | 82o 11' 00" | Buvramadichaur (Jumla) | changed status to GON- Basket on COD : 2076-09-20 |
15 | Rupagad HPP | 8.625 | Rup Gad | 28o 56' 12" | 29o 00' 02" | 82o 49' 10" | 82o 52' 11" | changed status to GON- Basket on COD : 2077-03-30 | |
16 | Sankuwa Khola 1 | 40.820 | Sankuwa | 27o 28' 44" | 27o 32' 45" | 87o 04' 00" | 87o 06' 04" | Bala,Tamku (Sankhuwasabha) | changed status to GON- Basket on COD : 2076-04-27 |