S NoProjectCapacity (MW)Appn NoAppn DatePromoterAddress Latitiude N Longitude E VDC/District Remarks
1Grid-Connected Solar Power Project, Lahan , 33 kV S/S4.00044362076-08-12Asian Tech Corporation Pvt. Ltd.Babarmahal, Kathmandu-11, Ph. no.-01-2291943 26o 42' 35"26o 43' 35"86o 25' 30"86o 27' 25" Lahan N.P. (Siraha)Survey Lic No: 761 Date: 2073-08-14
2Grid Connected Solar PV Project, Birendranagar Surkhet1.20065032081-02-04G.C.Solar Energy GroupBirendranagar-10, Nayagaun Surkhet28o 33' 36"28o 33' 43"81o 37' 34"81o 37' 43" BirendraNagar N.P. (Surkhet)Survey Lic No: 1075 Date: 2076-02-05
3Grid Connected Solar PV Project, Lamahi10.00068242081-02-20Pioneer Energy Pvt. LtdKathmandu-1327o 52' 30"27o 52' 50"82o 25' 36"82o 25' 50" Satbariya (Dang)Survey Lic No: 1081 Date: 2076-03-09
4Grid Connected Solar Electricity Project Part-2 Ganeshpur, K10.00068252081-02-20Positive Energy (Pvt.) LtdKathmandu Metropolitan City -13, Nepal27o 34' 57"27o 35' 08"82o 49' 20"82o 49' 41" Ganeshpur (Kapilbastu)Survey Lic No: 1245 Date: 2080-04-25
5Grid Connected Solar PV Project, Lamahi 110.00068262081-02-20Progressive Energy Pvt. LtdKathmandu-1327o 52' 30"27o 52' 42"82o 25' 54"82o 26' 08" Satbariya (Dang)Survey Lic No: 1082 Date: 2076-03-09
6Madhya Marsyangdi Solar Electricity Project, Lamjung1.60018942081-06-09Nepal Electricity AuthorityDurbar Marg , Kathmandu28o 11' 16"28o 11' 28"84o 25' 07"84o 25' 35" Sundarbajar (Lamjung)Survey Lic No: 1230 Date: 2079-10-26
7Jhupra Saurya Vidyut Project, Surkhet2.00018952081-06-09Nepal Electricity AuthorityDurbar Marg , Kathmandu28o 35' 52"28o 36' 07"81o 40' 23"81o 40' 41"Survey Lic No: 1229 Date: 2079-10-26
8Gandak Solar PV Project5.80018962081-06-09Nepal Electricity AuthorityDurbar Marg , Kathmandu27o 25' 16"27o 25' 46"83o 47' 12"83o 47' 42" Pratappur (Nawalparasi)Survey Lic No: 1264 Date: 2080-12-15
9Arga Saurya Vidyut Aayojana, Arghakhachi 10.00038582081-09-01Arga Bhagbati Ventures Private Limited Kathmandu - 16, Bohoratar27o 57' 47"27o 58' 12"83o 08' 24"83o 08' 48"Survey Lic No: 1243 Date: 2080-04-17
10Duhabi Solar Farm8.00060292081-11-15Global Energy & Construction Pvt. Ltd.Sagarmatha Complex, Bagwati Bahal, Naxal, KMC -01 26o 36' 05"26o 36' 15"87o 20' 00"87o 20' 15" Dangraha,Mrigauliya (Morang)Survey Lic No: 1275 Date: 2081-03-12
Total capacity for 10 projects = 62.6 MW