1 |
Electricity Production, Transmission and Distribution |
132 |
|
|
1 |
2052-02-28 |
2101-11-30 |
Nepal Electricity Authority |
Kathmandu |
Integrated power supply of Nepal |
INPS |
22 numbers of transmission lines from B.S. 2023 to 2047 |
2 |
Duhabi Bhantabari |
132 |
|
|
2 |
2052-04-16 |
2101-11-30 |
Nepal Electricity Authority |
Kathmandu |
Duhabi |
Bhantabari |
|
3 |
Kali Gandaki A Transmission Project |
132 |
|
|
3 |
2053-07-21 |
2101-11-30 |
Nepal Electricity Authority |
Kathmandu |
Kali Gandaki A PH |
Butwal/Lekhnath SS |
|
4 |
Upper Bhotekoshi |
132 |
|
|
4 |
2053-08-13 |
2093-07-30 |
Bhotekoshi Power Company |
|
|
|
|
5 |
Khimti - Sunkoshi-Bhaktapur-Chapali-Balaju |
132 |
105 |
440 |
5 |
2053-10-02 |
2101-11-30 |
Nepal Electricity Authority |
Kathmandu |
Khimti S/S |
Balaju S/S |
File no: 154 |
6 |
Chilime-Debighat |
66 |
|
|
6 |
2054-09-15 |
2104-03-31 |
Nepal Electricity Authority |
Kathmandu |
Chilime PH |
Debighat |
|
7 |
Kushaha-Dhalkbar (Double Circuit) |
132 |
|
|
7 |
2054-11-06 |
2101-11-30 |
Nepal Electricity Authority |
Kathmandu |
|
|
|
8 |
Hetauda-Dhalkbar Butwal-Bardghat(Double Circuit) |
132 |
181 |
55 |
8 |
2055-08-11 |
2101-11-30 |
Nepal Electricity Authority |
Kathmandu |
Hetauda |
Bardaghat |
|
9 |
Modi - Pokhara |
132 |
|
|
9 |
2055-09-30 |
2101-11-30 |
Nepal Electricity Authority |
Kathmandu |
|
|
|
10 |
Lalpur - Gadachauki |
132 |
|
|
10 |
2055-12-15 |
2101-11-30 |
Nepal Electricity Authority |
Kathmandu |
|
|
|
11 |
Indrawati - Panchkhal |
132 |
|
|
11 |
2057-06-27 |
2104-09-29 |
National Hydropower Co Pvt Ltd |
Kathmandu |
Indrawati III |
Panchkhal SS |
File no: 334 |
12 |
Middle Marsyangdi |
132 |
|
|
13 |
2059-04-29 |
2109-03-31 |
Nepal Electricity Authority |
Kathmandu |
|
|
File no: 476 |
13 |
Sunkoshi Small |
11 |
|
|
14 |
2060-01-05 |
2094-03-31 |
Sanima Hydropower Pvt Ltd |
Naksal, Kathmandu, P.O.Box 19739, Phone 014415314,4446442, Fax 01-4441277 |
|
|
|
14 |
Birgunj Corridor Reinforcement Project |
132 |
17 |
50 |
15 |
2060-05-26 |
2085-05-25 |
Nepal Electricity Authority |
Kathmandu |
Pathlaiya |
Parwanipur |
File no: 508 |
15 |
K-3 Transmission Line Project |
66 |
|
|
16 |
2061-05-08 |
2086-05-07 |
Nepal Electricity Authority |
Kathmandu |
|
|
File no: 535 |
16 |
Thankot-Chapagaun-Bhaktapur Transmission |
132 |
27 |
50 |
17 |
2061-08-17 |
2086-08-16 |
Nepal Electricity Authority |
Kathmandu |
Matatirth |
Harisiddi |
File no: 578 |
17 |
Butwal-Sunauli Transmission |
132 |
22 |
150 |
18 |
2062-03-19 |
2112-03-18 |
Nepal Electricity Authority |
Kathmandu |
Jogikuti NEA Substation |
India Nepal Boarder Sunnauli Substation |
|
18 |
Duhabi - Tankisinuwari Transmission |
33 |
|
|
19 |
2062-03-26 |
2097-03-25 |
Nepal Electricity Authority |
Kathmandu |
|
|
|
19 |
Khimti - Dhalkebar Transmission |
220 |
73 |
250 |
20 |
2063-10-19 |
2088-10-18 |
Nepal Electricity Authority |
Kathmandu |
Switchard of Khimti One HEP |
Dhalkebar Substation |
|
20 |
Chandranigahpur Transmission Network |
33 |
40.88 |
24 |
21 |
2064-08-27 |
2089-08-26 |
Nepal Electricity Authority |
Kathmandu |
Chandranigahpur NEA Substation |
Haripur NEA Substation |
|
21 |
Hewa Khola |
33 |
7.25 |
2.4 |
22 |
2065-04-16 |
2090-04-15 |
Barun Hydropower Development Pvt. Ltd. |
Phone 01-6226073 |
Switchayrd of Hewa HEP |
Tirtire NEA Substation |
|
22 |
Bardghat - Hetauda |
220 |
143 |
122 |
23 |
2065-09-14 |
2090-09-13 |
Nepal Electricity Authority |
Kathmandu |
Hetauda |
Bardaghat |
|
23 |
Balanch- Atteria 132 kV Transmission Line |
132 |
131 |
30 |
24 |
2065-09-29 |
2090-09-28 |
Nepal Electricity Authority |
Kathmandu |
Balanch |
Attariya NEA Substation |
Double Circuit Stringing later |
24 |
Kusum - Purandhara |
132 |
21.64 |
18 |
25 |
2066-02-11 |
2091-02-10 |
Dang Cement Industries |
PO Box 24347 Kathmandu |
Lamahi NEA Substation |
Switchyard of Dang Cement Factory |
Transferred to NEA on 2067-12-01 |
25 |
Chaku Khola |
33 |
2 |
10 |
26 |
2066-03-25 |
2091-03-24 |
Laughing Buddha Power Nepal Pvt Ltd |
Hadigaun, Kathmandu, Phone 4429533, 4411153 |
Switchard of Middle Chaku HEP |
Switchyard of Lower Chaku HEP |
|
26 |
Baramchi - Sunkoshi |
33 |
15 |
10 |
27 |
2066-09-04 |
2091-09-03 |
Unique Hydel Co Pvt Ltd |
PO Box 19554, Phone 4672598 |
Switchyard of Baramchi Khola HEP |
Sunkoshi NEA Substation |
|
27 |
Butwal - Kohalpur (D/C stringing) |
132 |
|
100 |
28 |
2067-02-19 |
2101-11-30 |
Nepal Electricity Authority |
Kathmandu |
|
|
|
28 |
Singati - Jagat (Sipring Khola HP) |
33 |
|
10 |
29 |
2067-11-30 |
2092-11-29 |
Synergy Power Development Co |
Kathmandu |
|
|
|
29 |
Kabeli Corridor |
132 |
|
150 |
30 |
2067-12-25 |
2092-12-24 |
Nepal Electricity Authority |
Kathmandu |
|
|
|
30 |
Bijaypur-1 33 kV Transmission |
33 |
|
4.5 |
31 |
2067-12-25 |
2092-12-24 |
Bhagwati Hydropower Development Pvt Ltd |
|
|
|
|
31 |
Singati-Lamosanghu |
132 |
|
100 |
32 |
2068-01-09 |
2093-01-08 |
Nepal Electricity Authority |
Kathmandu |
|
|
|
32 |
Anbukhaireni - Dumre - Damauli |
132 |
|
24 |
33 |
2068-01-09 |
2093-01-08 |
Nepal Electricity Authority |
Kathmandu |
|
|
|
33 |
Kamane - Laxmipur Transmission |
33 |
|
24 |
34 |
2068-01-19 |
2093-01-18 |
Nepal Electricity Authority |
Kathmandu |
|
|
|
34 |
Dumre-Damauli |
132 |
|
50 |
35 |
2068-02-19 |
2093-02-18 |
Nepal Electricity Authority |
Kathmandu |
|
|
|
35 |
Mai HEP Transmission |
132 |
12 |
22 |
36 |
2068-03-02 |
2093-03-01 |
Sanima Hydropower Pvt Ltd |
Naksal, Kathmandu, P.O.Box 19739, Phone 014415314,4446442, Fax 01-4441277 |
Switchayrd of Mai HEP |
Godak NEA Substation |
|
36 |
Dhalkebar - Bhittamod Cross-border |
400 |
39 |
400 |
37 |
2068-05-08 |
2093-05-07 |
Nepal Electricity Authority |
Kathmandu |
Dhalkebar NEA Substation |
Nepal India Boarder Mujjafarpur |
|
37 |
Larcha-Chaku 33kV (Bhairabkund HP |
33 |
6.2 |
3 |
38 |
2068-06-15 |
2093-06-14 |
Bhairabkund HP |
Kathmandu |
Switchyard of Bhairavkund Khola HEP |
Chaku |
|
38 |
Kulekhani 3 |
132 |
0.5 |
14 |
39 |
2068-07-17 |
2093-07-16 |
Nepal Electricity Authority |
Kathmandu |
Switchyard of Kulekhani 3 HEP |
Switchyard of Kulekhani 2 |
|
39 |
Hetauda - Kulekhani - Siuchatar |
132 |
42 |
32 |
40 |
2068-08-06 |
2101-11-30 |
Nepal Electricity Authority |
Kathmandu |
Hetauda NEA Substation |
Switchatar Substation |
|
40 |
Lower Modi |
132 |
7.7 |
10 |
41 |
2068-08-22 |
2093-08-21 |
United Modi |
Kathmandu |
Switchyard of Modi 1 HEP |
Switchyard of Modi Khola HEP |
|
41 |
Kohalpur - Mahendranagar Second Circuit |
132 |
198 |
100 |
42 |
2068-08-25 |
2101-11-30 |
Nepal Electricity Authority |
Kathmandu |
Kohalpur Substation |
Lalchowk NEA Substation |
|
42 |
Tadi Khola |
33 |
8.4 |
5 |
43 |
2069-04-22 |
2094-04-21 |
Adishakti Vidyut Co |
Kathmandu |
Switchyard of Tadi Khola HEP |
Chaughda NEA Substation |
|
43 |
Mabu - Ilam 132 kV Transmission |
132 |
18.5 |
20 |
44 |
2069-08-17 |
2094-08-16 |
Mai Valley Hydro Power Pvt Ltd |
|
|
|
|
44 |
Hetauda - Dhalkebar & Duhabi 400 kV |
400 |
285 |
1000 |
45 |
2069-10-03 |
2094-10-02 |
Nepal Electricity Authority |
Kathmandu |
|
|
|
45 |
Mailung Khola Transmission Line |
66 |
3 |
6 |
46 |
2070-01-10 |
2095-01-09 |
Mailung Khola Jalbidyut Company Pvt. Ltd. |
Subarna Samsher Marg, Baluwatar, Phone 4419703 |
Milung Dobhan |
Ramche 66 kV TL |
|
46 |
Pikhuwa Khola Transmission Line Project |
33 |
3.5 |
2.5 |
47 |
2070-02-08 |
2095-02-07 |
Eastern Hydropower Pvt. Ltd. |
Kathmandu |
Powerhouse at Bhojpur VDC |
Panitanki Substation |
|
47 |
Upper Tamakoshi Transmission Line Project |
220 |
47 |
577.8 |
48 |
2070-05-21 |
2095-05-20 |
Upper Tamakoshi Hydropower Limited |
Gyaneshwor, kathmandu, PO Box: 36070, Phone: 4424694 |
Lamabagar |
Khimti Substation |
|
48 |
Upper Trishuli 3A Transmission Line Project |
220 |
45 |
309 |
49 |
2070-05-27 |
2095-05-26 |
Nepal Electricity Authority |
Durbarmarg, Kathmandu |
Upper trishuli 3A Project |
Matatirtha Substation |
|
49 |
Lamahi-Ghorahi Transmission Line Project |
132 |
12.1 |
100 |
50 |
2070-07-05 |
2095-07-04 |
Nepal Eletricity Authority |
Durbarmarg, kathmandu |
Lamahi |
Ghorahi |
|
50 |
Solu corridor 132 kV Transmission Line Project |
132 |
88.4 |
352 |
51 |
2070-09-14 |
2095-09-13 |
Nepal Electricity Authority |
Durbarmarga, Kathmandu |
Mirchaiya |
Tingla |
|
51 |
Hugdi - Birbas 33 kV Line |
33 |
12 |
5 |
52 |
2071-05-26 |
2096-05-25 |
Ruru Jalvidyut Pariyojana P ltd |
POB 8416 Samakhusi 29 Kathmandu, Ph 4389703 |
Switchyard of Hungdi HEP |
Birbas NEA Substation |
|
52 |
Tungun Thosne and Khani Khola |
33 |
16.214 |
6.36 |
53 |
2071-05-29 |
2096-05-28 |
Khani Khola Hydropower Company |
226 Milapmarg Vishal Nagar, PoB 8975 Kathmandu, Ph 01-4417947, 4436325 |
Tungun Thosne Switch Yard |
Malta NEA Substation |
|
53 |
Siuri Khola HEP 33 kV Transmission Line |
33 |
7.5 |
5 |
57 |
2071-08-25 |
2096-08-24 |
Nyadi Group Pvt Ltd |
P.O. Box: 14165, Tel: 01-4102651, Fax: 01-43732020 |
Siuri SS, Bhulbhule |
Khudi SS, Thakanbesi |
|
54 |
Solu HEP 132 KV |
132 |
2.6 |
23.5 |
54 |
2071-10-04 |
2096-10-03 |
Upper Solu Hydro Electric Co.Pvt.Ltd. |
Narayan Chour |
Switchyard of Solu HEP |
Lamane NEA Substation |
|
55 |
Koshi Corridor |
220 |
220 |
850 |
55 |
2071-10-09 |
2096-10-08 |
Nepal Electricity Authority |
Darbar Marg Kathmandu, POB 10020 |
Dhunge Bisauni |
Sunsari Jhokraha |
|
56 |
Nugad Gad HP |
33 |
5 |
8.5 |
56 |
2071-10-09 |
2096-10-08 |
Api Power Co. Ltd |
Trade Tower, Thapathali KTM,5111035 |
Switchyard |
Darchula Sikhar |
|
57 |
Chhandi Khola & Upper Chhandi Khola Joint HEP Transmission Line |
33 |
10 |
6 |
58 |
2071-11-15 |
2096-11-14 |
Chhyangdi Hydropower Limited |
Gairidhara Kathmandu |
Switchyard |
udipur |
Survey Lic No: 0 Date: 0000-00-00 |
58 |
Daram Khola A 33kV |
33 |
5 |
2.5 |
59 |
2072-03-31 |
2097-03-30 |
Sayapatri Hydropower P Ltd |
Kathmandu |
Switchyard |
harichaur |
Survey Lic No: 158 Date: 2069-07-15 |
59 |
Upper Madi 132kV Transmission Line Project |
132 |
10 |
118 |
60 |
2072-06-11 |
2097-06-10 |
Madi Power Pvt. Ltd. |
Gorkha Complex, Min Bhavan, PO Box: 2581, Phone: 014106507, 014106731 Fax: 01410 |
Sildujure |
Lekhnath Substation |
Survey Lic No: 185 Date: 2070-06-06 |
60 |
Jogmai Khola HPP Joint Transmission Line Project |
33 |
10.88 |
19 |
61 |
2072-06-13 |
2097-06-12 |
Sanvi Energy Pvt. Ltd. |
Manbhavan, Lalitpur, PO Box: 8975EPC1341, Phone: 5532860 |
Switchyard of Jogmai Khola Project |
Proposed Godak Substation |
Survey Lic No: 173 Date: 2069-12-29 SC & DC both |
61 |
Samundratar-Trishuli 3B Hub 132 kV Transmission Line Project |
132 |
25 |
100 |
62 |
2072-07-02 |
2097-07-01 |
Nepal Electricity Authority |
Durbarmarg, Kathmandu |
Samundratar |
Trishuli 3B Hub-stationt |
Survey Lic No: 181 Date: 2070-04-20 |
62 |
Hewa Khola A 132 kV Transmission Line |
132 |
15 |
4.5 |
63 |
2072-07-20 |
2097-07-19 |
Panchthar Power Company P |
Kathmandu |
Switchyard |
Fidim Substation |
Survey Lic No: 167 Date: 2069-10-08 |
63 |
Bhulbhule-Madhya Marsyangdi TL Project |
132 |
22 |
100 |
64 |
2072-09-02 |
2097-09-01 |
Nepal electricity Authority |
Durbarmarg |
Upper Marsyangdi A HEP Switchyard |
Madhya Marsyangdi |
Survey Lic No: 203 Date: 2071-03-31 |
64 |
Thapa Khola Transmission Line Project |
33 |
4 |
11.2 |
65 |
2072-10-17 |
2097-10-16 |
Mount Kailash Energy Pvt. Ltd. |
P. O. Box: 12107, Banasthali-16, Kathmandu. Phone: 014387869, Fax: 014350870 |
Thapa Khola Project P/H |
Proposed Koban Substation |
Survey Lic No: 184 Date: 2070-06-06 |
65 |
Daraudi A 33 kV Transmission Line Project |
33 |
17 |
6 |
66 |
2072-12-01 |
2097-11-30 |
Daraudi Kalika Hydropower Pvt.Ltd. |
Baluwatar 4, kathmandu, kalika tower , 6th floor, P.O.Box 21534, Phone 4439152 |
Switchyard at chanute |
Gorkha, Substation |
Survey Lic No: 0 Date: 0000-00-00 |
66 |
Trishuli 3B Hub Substation |
220 |
0.744 |
400 |
67 |
2072-12-07 |
2097-12-06 |
Nepal Electricity Authority |
Kathmandu |
Upper 3A Matatirtha 220kV |
Matatirtha Busbar |
Survey Lic No: 161 Date: 2069-08-12 |
67 |
Lower Solu HEP 132 kV Transmission Line |
132 |
|
82 |
68 |
2072-12-22 |
2097-12-21 |
Essel Clean Solu Hydropower Pvt Ltd |
Kathmandu |
power house |
Lamane substation |
Survey Lic No: 235 Date: 2072-09-17 |
68 |
Marsyandi - Kathmandu 220 KV Transmission line Project |
220 |
85 |
550 |
69 |
2072-12-22 |
2097-12-21 |
Nepal Electricity Authority |
PBO 10020, Kathamndu |
Aabukhareni |
kathmandu |
|
69 |
Chake Khola |
33 |
9.55 |
2.83 |
70 |
2073-01-12 |
2098-01-11 |
Grjyang Upatyaka HP L |
New Bazar. Ph No 43822205 |
switchyard |
Jiri |
Survey Lic No: 218 Date: 2071-10-04 |
70 |
Chilime Hub Substation and 220 kV TL Project |
220 |
26.5 |
500 |
71 |
2073-01-14 |
2098-01-13 |
Nepal Electricity Authority |
P.O.B.10020, Durbarmarga Kathmandu |
Chilime Hub |
Trishuli 3 B Hub Substation |
Survey Lic No: 164 |
71 |
Upper Chaku A HEP 132 kV Transmission Line Project |
132 |
15 |
82.46 |
72 |
2073-02-04 |
2098-02-03 |
Shiva Shree Hydropower PLtd |
Kathmandu |
Respective switchyard of Project |
Lamo Sanghu Substation |
Survey Lic No: 179 Date: 2070-02-10;Double ckt(Upper Chaku A,22.2MW+Liping,16.26MW+Bhotekoshi-1,44MW- s/w of Upper chaku A) |
72 |
sardi khola 33 kv Transmission line Project |
33 |
13.27 |
6.9 |
73 |
2073-02-11 |
2098-02-10 |
Mandakini Hydropower Pvt.Ltd. |
GPO Box: 7327, Katmandu |
Power house |
New hemja baskot |
Survey Lic No: 213 Date: 2071-08-26;sardi(4)+upper sardi(2.9) |
73 |
Kusma Tallo Modi ( Kaligandaki Corridor) |
132 |
6.05 |
100 |
74 |
2073-03-27 |
2098-03-26 |
Nepal Electricity Authority |
Darbar Marg Kathmandu, POB 10020 |
Khurkot NEA Substation |
Switchyard of United Modi HEP |
Survey Lic No: 215 Date: 2071-09-17 |
74 |
Kaligandaki Corridor 220 kV Transmission Line |
220 |
40 |
500 |
75 |
2073-04-07 |
2098-04-06 |
Nepal Electricity Authority |
Kathmandu |
Kushma substation |
daana substation |
Survey Lic No: 202 Date: 2071-03-20 |
75 |
Rasuwagadhi (Bhotekoshi-Trishuli) 132kV TL |
132 |
9.55 |
111 |
76 |
2073-08-17 |
2098-08-16 |
Chilime Hydropower Co. Ltd. |
Gyaneswor, Po.B.No. 25210 |
Powerhouse |
Chilime Hub Substation |
Survey Lic No: 116 Date: 27-02-2067 |
76 |
Mistri HEP Mistri-Dana 132 kV Transmission Line |
132 |
3.5 |
42 |
77 |
2073-10-10 |
2098-10-09 |
Robust Energy Pvt Ltd |
P.O. Box: 21729, Panipokhari, KTM, Tel: 4437705, 4441648, 6226870 |
Powerhouse/Switchyard at nyarchang V.D.C |
daana substation |
Survey Lic No: 126 Date: 2067-04-21 |
77 |
Khimti - Grajyang 132 kV Transmissin Line |
132 |
30.98 |
100 |
78 |
2073-10-20 |
2098-10-19 |
Nepal Electricity Authority |
Kathmandu |
NEA Hub Substation in Dolakha |
Chuchure Hub Substation |
Survey Lic No: 189 Date: 2070-10-27 |
78 |
Midim khola (karapu) HPP 33 KV TL Project |
33 |
7.6 |
3 |
79 |
2073-11-10 |
2098-11-09 |
M/s Union Hydropower Pvt.Ltd. |
PBO 12637, Kathamndu |
Proposed power house |
Ram Bazzar Substation |
Survey Lic No: 241 Date: 12-22-2072 |
79 |
Kabeli B1,132 KV Transmission line Project |
132 |
5 |
59.84 |
80 |
2073-11-24 |
2098-11-23 |
Arun Kabeli Power Limited |
GPO Box: 11039, Katmandu |
Switchyard |
Amarpur Substation |
Survey Lic No: 219 Date: 2071-12-11 |
80 |
Molung Khola HEP 33 kv Transmission line |
33 |
10 |
7 |
81 |
2074-01-11 |
2099-01-10 |
molung hydropower Pvt.Ltd |
GPO Box: 5813, Katmandu |
Porposed power House at harkapur VDC |
Siddicharan municipality |
Survey Lic No: 223 Date: 2072-03-24 |
81 |
Lower Hewa Khola Transmission Line Project |
132 |
3.2 |
21.6 |
82 |
2074-02-02 |
2099-02-01 |
Mountain Hydro Nepal pvt. Ltd. |
Kalanki, Kathmandu-14 |
Powerhouse of Lower Hewa Khola Project |
Phidim Substation |
Survey Lic No: 257 Date: 01-07-2073 |
82 |
koshi corridor 220 kv Transmission line project |
220 |
31.5 |
850 |
83 |
2074-02-30 |
2099-02-29 |
Nepal Electricity Authority |
P.O.B.10020, Durbarmarga Kathmandu |
Basantapur S/S |
Changey S/S at Dhungesangu |
Survey Lic No: 0 Date: 0000-00-00 |
83 |
Nyadi 132kV Transmission Line Project |
132 |
9.408 |
30 |
84 |
2074-03-11 |
2099-03-10 |
Nyadi Hydropower Limited |
gangadevi marg, buddhanagar, P.B.no. 26305, 4781776 |
Bahundada PH |
Middle Marsyandi switchyard |
Survey Lic No: 271 Date: 08-09-2073 |
84 |
New Modi Lekhnath 132 kV Transmission Line |
132 |
42.198 |
130 |
85 |
2074-05-19 |
2099-05-18 |
Nepal Electricity Authority |
Kathmandu |
New Modi substation |
Lekhnath substation |
Survey Lic No: 146 Date: 2069-01-25 |
85 |
Kapadi Gad HEP 33 kV Transmission Line |
33 |
28 |
3.33 |
86 |
2074-05-27 |
2099-05-26 |
Salmani Devi Hydropower Pvt. Ltd. |
Dhungaadda, Tinthana-07, Ktm |
Respective Switchyard of the project at |
Budar Substation NEA, Budar Bajar |
Survey Lic No: 191 Date: 2070-11-04 |
86 |
Upper Khorunga Transmission Line Project |
33 |
4.7 |
7.5 |
87 |
2074-06-01 |
2099-05-31 |
Terhathum Power Company Pvt. Ltd. |
PO Box: 14130, Kathmandu, Aradhana Complex, Baagbazaar. Phone: 014240661, Fax: 0 |
Powerhouse of Upper Khorug Project |
Jiri-Khimti Substation |
Survey Lic No: 207 Date: 2071-05-02 |
87 |
Bagmati-Kulekhani Transmission Line |
66 |
13 |
32 |
88 |
2074-06-01 |
2099-05-31 |
Mandu Hydropower Limited |
Kamaladi 31 Kathmandu |
Switchyard of Bagmati HPP |
Kulekhani-I substation |
Survey Lic No: 170 Date: 2069-11-14;Single ckt,Bear conductor |
88 |
Kushwa-Biratnagar 132 kV Transmission Line |
132 |
22.8 |
200 |
89 |
2074-07-17 |
2099-07-16 |
Nepal Electricity Authority |
PBO 10020, Kathamndu |
Jhokharha, Sunsari |
Belgachhiya S/S of NEA, Sunsari |
Survey Lic No: 238 Date: 2072-12-02 |
89 |
Tamakoshi-Kathmandu Transmission Line |
400 |
100 |
500 |
90 |
2074-07-27 |
2099-07-26 |
Nepal Electricity Authority |
Durbarmarg, Kathmandu |
Fulase, Ramechhap |
Mulpani, Kathmandu |
Survey Lic No: 177 Date: 2070-01-31 |
90 |
Chautara-Lamosanghu 33 kV TL Project |
33 |
6 |
6.4 |
91 |
2074-08-04 |
2099-08-03 |
Nepal Electricity Authority |
PBO 10020, Kathamndu |
Chautara Substation |
Lamosanghu Substation |
Survey Lic No: 261 Date: 2073-07-25 |
91 |
Lower khare khola Transmission line |
33 |
5.36 |
11 |
92 |
2074-09-18 |
2099-09-17 |
Universal Power Company Limited |
Blue Star Complex, Tripureshwore |
Power house of lower khare at Bigu |
NEA substation Singati |
Survey Lic No: 237 Date: 2072-12-02 |
92 |
Upper Hewa Khola Saanaa 33 kV TL Project |
33 |
11 |
8.5 |
93 |
2074-09-26 |
2099-09-25 |
Upper Hewa Khola Hydropower Company Pvt. Ltd. |
Kathmandu-32, Anaamnagar. Phn. No. 01-4102856 |
Jaljale Powerhouse |
Baneswor Substation |
Survey Lic No: 252 Date: 2073-03-07 |
93 |
Sanjen Transmission Line Project |
132 |
1.135 |
42.5 |
94 |
2074-10-23 |
2099-10-22 |
Sanjen Jalbidyut Company Limited |
PO Box: 12667, Lazimpat, Kathmandu , Phone: 014002049, Fax: 014002048 |
Switchyard of Sanjen Project |
Chilime Hub Substation |
Survey Lic No: 200 Date: 2071-03-06 |
94 |
Marsyangdi Corridor Udipur-New Bharatpur substation |
220 |
52.08 |
1600 |
95 |
2074-11-11 |
2099-11-10 |
Nepal Electricity Authority |
PBO 10020, Kathamndu |
Tanahu Markichowk Substation |
New Bharatpur Substation |
Survey Lic No: 234 Date: 2072-09-02 |
95 |
Kaligandaki corridor (Kusma New Butwal) |
220 |
65 |
1000 |
96 |
2074-11-15 |
2099-11-14 |
Nepal Electricity Authority |
Darbar Marg Kathmandu, POB 10020 |
Kusma |
Butwal |
Survey Lic No: 214 Date: 2071-09-07 |
96 |
Dordi Corridor 132 kV Transmission Line |
132 |
15 |
160 |
97 |
2074-12-13 |
2099-12-12 |
Nepal Electricity Authority |
PBO 10020, Kathamndu |
Dhodeni VDC |
Udipur Hub Substation |
Survey Lic No: 240 Date: 2072-12-22 |
97 |
Sanjen to Chilime 66kV Tr. Ln. Rasuwa district |
66 |
5 |
11 |
98 |
2075-01-07 |
2100-01-06 |
Shree Chilime Jal vidhut Company |
520 Kalika Marg kathmandu |
Sanjen Hydropower project |
Chilime Switch yard |
Survey Lic No: 66 Date: 2063-10-28 Voltage is upgraded up to 132kV |
98 |
Tanahu hydropower 220 kV transmission line |
220 |
36.5 |
140 |
99 |
2075-01-12 |
2100-01-11 |
Tanahu Hydropower Limited |
Trade Tower 4th floor, Thapathali , Kathmandu, Tel:- 01-5111117, 5111118 |
powerhouse of Tanahu hydro |
new bharatpur substation NEA |
Survey Lic No: 317 Date: 2074-08-22 |
99 |
Puwa Khola one Jal vidhut 33 Kv Transmission line |
33 |
4 |
5 |
100 |
2075-02-08 |
2100-02-07 |
Shree Puwa Khola one Hydropower Pvt.Ltd |
Baluwatar -2,Kathmandu |
Puwa Khola Hydropower Project |
Godak Nea Substation |
Survey Lic No: 192 Date: 2070-12-05 |
100 |
Kohalpur-Dampur 33kV TL |
33 |
5.3 |
6.4 |
101 |
2075-03-04 |
2100-03-03 |
Nepal Electricity Authority |
|
Fattepur VDC, Tingharwa, Bheri |
Alinagar, Binauna VDC |
Survey Lic No: 284 Date: 2074-01-17 |
101 |
Bardaghat Sardi 132 kV Tr. Ln.Nawalparsi District |
132 |
18 |
200 |
102 |
2075-04-04 |
2100-04-03 |
Nepal Electricity Authority |
Main office,Darbarmarg,Kathmandu |
Bardaghat |
Sardi |
Survey Lic No: 263 Date: 2073-08-09 |
102 |
Matatirtha-Naubise Transmission line |
33 |
11.5 |
12.8 |
103 |
2075-04-29 |
2100-04-28 |
Nepal Electricity Authority |
Durbarmarg, Kathmandu |
Matatirtha, Kathmandu |
Naubise, Dhading |
Survey Lic No: 330 Date: 2074-11-09 |
103 |
Matatirtha-Malta transmission line |
33 |
34 |
6.45 |
104 |
2075-04-29 |
2100-04-28 |
Nepal Electricity Authority |
Durbarmarg, Kathmandu |
Matatirtha substation at Kathmandu |
Malta VDC at Lalitpur |
Survey Lic No: 329 Date: 2074-11-06 |
104 |
Rudi Khola Transmission Line Project |
33 |
3.5 |
15.4 |
105 |
2075-05-04 |
2100-05-03 |
Bindhabasini Hydropower Development Company Pvt. Ltd. |
Naya Baneshwor, Kathmandu-10, PO Box: 10242, Kathmandu. Phone: 4785671 |
Powerhouse of Rudi A and Rudi B Projects |
Proposed NEA Substation at Mijure |
Survey Lic No: 255 Date: 2073-04-31 |
105 |
Burtibang to Gorusinghe ,Kapilvastu District |
132 |
83.376 |
227.17 |
106 |
2075-06-16 |
2100-06-15 |
Nepal Electricity Authority |
Main office,Darbarmarg,Kathmandu |
Jitpur Substation |
Burtibang Substation |
Survey Lic No: 276 Date: 2073-09-29 |
106 |
Kushaha Kataiya 132kV |
132 |
14 |
100 |
107 |
2075-07-20 |
2100-07-19 |
Nepal Electricity Authority |
PBO 23330, Kathmandu |
Kushaha |
Kataiya |
Survey Lic No: 253 Date: 2073-02-28 ; End Point is amended based on survey License 253 on 2077-04-26 |
107 |
Raksaul - Parwanipur 132 kV Transmission Line Project |
132 |
22 |
150 |
108 |
2075-07-20 |
2100-07-19 |
Nepal Electricity Authority |
PBO 20225, Kathmadu |
Parwanipur |
Rakshwal |
Survey Lic No: 249 Date: 2073-02-06 |
108 |
Arun-3 HEP Construction power 33kV TL |
33 |
46.58 |
10 |
110 |
2075-07-20 |
2100-07-19 |
SJVN Arun 3 Power Developemnt Company Pvt. Ltd. |
Madhyapur thimi lokanthali bhaktapur |
Arun -3 Hydro Power Project switchyard |
Tirtire NEA substation |
Survey Lic No: 282 Date: 2073-12-07 |
109 |
Khani Khola-1 Transmission Line Project |
132 |
20 |
40 |
109 |
2075-08-09 |
2100-08-08 |
Shree Green Life Hydro power Ltd. |
Kamalpokhari, Kathmandu, PO Box: 3970, Phone: 5549912 |
Powerhouse of Khani Khola-1 HPP |
Singati NEA Substation |
Survey Lic No: 256 Date: 2073-06-06 |
110 |
Suri Khola Hydro Power Project Transmission Line Project |
33 |
6.9 |
14 |
111 |
2075-08-17 |
2100-08-16 |
Shree Suri Khola Hydropower Pvt. Ltd. |
Tripureshwor, Kathmandu |
Switchyard of Suri Khola Hydro Power Pro |
Singati NEA Substation |
Survey Lic No: 205 Date: 2071-04-20 |
111 |
Marsyandi Corridor (Dharapani Udipur)Manag District |
220 |
45.25 |
1600 |
112 |
2075-10-02 |
2100-10-01 |
Nepal Electricity Authority |
Main office,Darbarmarg,Kathmandu |
Dharapani |
Udipur |
Survey Lic No: 234 Date: 2072-09-02 Extended upto 2075-09-01 |
112 |
Sunwal 132 KV TL |
132 |
0.1 |
100 |
113 |
2075-10-13 |
2100-10-12 |
Nepal Electricity Authority |
|
|
|
Survey Lic No: 295 Date: 2074-04-23 |
113 |
Arun-3 HPP ,Sankhuwashabha District |
400 |
217 |
900 |
114 |
2075-10-25 |
2105-10-24 |
Shree SJVN Arun 3 Power Developemnt Company Pvt. Ltd. |
Madhyapur Thimi |
Arun 3 HPP |
Dhalkebar NEA Substation to Nepal India |
Survey Lic No: 100 Date: 2066-02-08 |
114 |
Rukum Gad Hydro Power Project |
33 |
20.78 |
5 |
115 |
2075-11-03 |
2100-11-02 |
Shree Rapti Hydro and General construction Pvt.Ltd. |
Tripureshwor-11,Kathmandu |
Switchyard of Rukum Gad Hydro Power Pro |
Musikot NEA Substation, |
Survey Lic No: 225 Date: 2072-03-24 |
115 |
Butwal Gorusinghe Lumbini,Rupandehi |
132 |
19 |
200 |
116 |
2075-12-11 |
2100-12-10 |
Nepal Electricity Authority |
Main office,Darbarmarg,Kathmandu |
Jogikuti substation |
Mainahiya substation |
Survey Lic No: 352 Date: 2075-03-25 |
116 |
Upper Trishuli 1 HEP 220 kV T L |
220 |
1.184 |
216 |
117 |
2076-02-09 |
2109-07-22 |
Nepal Water and Energy Development Company P Ltd |
Naksal, Kathmandu, 01-4412257,4412229 |
Haku VDC, Rasuwa, switchyard of Upper Tr |
Nearest Angle Point to Chilime Trishuli |
Survey Lic No: 281 Date: 2073-11-09 |
117 |
Middle Bhotekoshi Hydro Power Project |
220 |
5 |
102 |
118 |
2076-04-28 |
2101-04-27 |
Madhya Bhotekoshi Jalavidyut Company Ltd. |
GPO Box: 23599, Katmandu |
Switchyard of Maghya Bhotekoshi HPP |
Barhabise NEA Substation |
Survey Lic No: 222 Date: 2072-02-12 Er.Vijay |
118 |
Upper Balephi A HPP,Sindhupalchowk Disrict |
132 |
21 |
43.27 |
119 |
2076-05-10 |
2101-05-09 |
Shree Balephi Hydropower Ltd. |
Ratopool,Kathmandu |
Upper Balephi A HPP (Sindhupalchowk) |
Lamosangu Substation |
Survey Lic No: 372 Date: 2075-07-20 |
119 |
Sunkuda to Balanch |
132 |
40 |
64.49 |
120 |
2076-06-09 |
2101-06-08 |
Shree kalanga hydro pvt.ltd |
Dhobighat 3 |
Switchyard of Kalangad HPP to Upper Kala |
Upper Sanigad Switchyard to Balach NEA S |
Survey Lic No: 357 Date: 2075-04-13 Er.Vijay |
120 |
Ghatte Khola Hydropower project 33Kv Transmission Line |
33 |
15 |
5 |
121 |
2076-06-15 |
2101-06-14 |
Shree Manakamna Enginering Hydropower Pvt.Ltd. |
Shankhmul Marg ,Naya Baneshwor ,Kathmandu |
Switchyard of Ghatte Khola Hydropower Pr |
Singati NEA Substation(Dolakha) |
Survey Lic No: 345 Date: 2075-02-15 |
121 |
Dhalkebar Loharpati 132 kV Transmission Line |
132 |
18.85 |
200 |
122 |
2076-07-08 |
2101-07-07 |
Nepal Electricity Authority |
PBO 20225, Kathmadu |
Dhalkebar NEA Substation (Dhanusha) |
Loharpati NEA Substation (Mahottari) |
Survey Lic No: 291 Date: 2074-03-28 |
122 |
Likhu-IV |
220 |
19.15 |
52.4 |
123 |
2076-07-20 |
2101-07-19 |
Green Venture Pvt. Ltd. |
Triveni Complex, Putalisadak, Kathmandu, Ph: 01-4224074, Fax: 01-4266133 |
Likhu-IV power house at Ragani, Okhaldhu |
New Khimti substation NEA, Ramechap,Fula |
Survey Lic No: 297 Date: 2074-04-31 |
123 |
Kamane Substaion to Ridhi Sidhi Cement Factory |
33 |
1.7 |
30 |
124 |
2076-08-18 |
2101-08-17 |
Nepal Electricity Authority |
Main office,Darbarmarg,Kathmandu |
Kamane Substation (Makwanpur) |
Ridhi Sidhi Cement Factory (Makwanpur) |
Survey Lic No: 346 Date: 2075-02-25 |
124 |
Solu Khola HEP 132 kV Transmission Line Project |
132 |
12 |
86 |
125 |
2076-09-11 |
2101-09-10 |
Shree Sahas Urja Limited |
Hatisaar-1Ktm 014419182,4419183,4422756 |
Switchyard of Proposed power house at Pa |
Lamane Tingla NEA Substation(Solukhumbu) |
Survey Lic No: 246 Date: 2072-12-30 Er.Vijay |
125 |
Upallo Khimti 132kV Transmission Line Project |
132 |
1.7 |
12 |
126 |
2076-11-07 |
2101-11-06 |
Himalayan Urja Bikas Company Pvt. Ltd. |
Tinkunne, Kathmandu-35, 01-4111853,01-4111674 |
Chuchure Ramechhap, Powerhouse/switchyar |
Garjang Substation |
Survey Lic No: 267 Date: 2073-08-12 |
126 |
Upper Khimti 2 Hydropower Project |
132 |
1.5 |
7 |
127 |
2076-11-07 |
2101-11-06 |
shree Himalayan Urja Bikas Company Ltd. |
Subidhanagar ,Kathmandu |
Upper Khimti 2 Switchyard |
Garjyang NEA Substation |
Survey Lic No: 387 Date: 2075-11-26 |
127 |
Likhu-2 Hydropower Project |
132 |
5.403 |
132 |
128 |
2076-11-14 |
2101-11-13 |
Global Hydropower Associate Pvt.Ltd. |
4th floor ,Laxman Babu Bhawan ,Naxal,Kathmandu,Nepal |
Switchyard of Project (Ramechap) |
Switchyard of Likhu A (Solukhumbu) |
Survey Lic No: 416 Date: 2076-06-24 |
128 |
Super Dordi Hpp |
132 |
5.6 |
54 |
129 |
2076-11-14 |
2101-11-13 |
Shree Peoples Hydropower Co.Pvt.Ltd |
Anamnagar,Kathmandu |
Super Dordi Hpp Switchyard (Lamjung) |
Kirtipur Substation (Lamjung) |
Survey Lic No: 233 Date: 2072-07-20 |
129 |
Surkhet - Bijaura |
33 |
40 |
3 |
130 |
2076-11-28 |
2101-11-27 |
Nepal Electricity Authority |
Main office,Darbarmarg,Kathmandu |
Birendranagar Surkhet |
Bijaura |
Survey Lic No: 411 Date: 2076-05-17 |
130 |
Dadakhet-Rahughat 132kV TL |
132 |
25.4 |
200 |
131 |
2077-01-30 |
2102-01-29 |
Nepal Electricity Authority |
|
Dadakhet S/S |
Rahughat S/S |
Survey Lic No: 285 Date: 2074-01-20 |
131 |
Upper Rahughat and Rahughat Mangale 220 kV Transmission Line Project |
220 |
15 |
106.8 |
132 |
2077-01-30 |
2102-01-29 |
Tundi Power Company Pvt . Ltd. |
PO Box 6341, Nayabato, Sanepa-3, Lalitpur |
Rahughat mangale Switchyard |
NEA Rahu Piple Substation |
Survey Lic No: 199 Date: 2071-03-04 Er.Vijay |
132 |
Kohalpur Surkhet 132kV ,Banke |
132 |
55 |
100 |
133 |
2077-02-29 |
2102-02-28 |
Nepal Electricity Authority |
Main office,Darbarmarg,Kathmandu |
Kohalpur Substation |
Latikoyli Substation |
Survey Lic No: 354 Date: 2075-04-04 |
133 |
Taksar-Pikhuwa hydropower 33 kV transmission line |
33 |
7.6 |
8 |
134 |
2077-03-12 |
2102-03-11 |
Taksar-Pikhuwa Hydropower Pvt. Ltd. |
Gairigaun, Kathmandu |
Taksar-Pikhuwa Hydropower switchyard |
Panitanki substation at Manebhanjyang |
Survey Lic No: 310 Date: 2074-07-12 |
134 |
Likhu-A HEP Transmission project 132 kv |
132 |
29 |
161.04 |
135 |
2077-03-19 |
2102-03-18 |
Numbur Himalaya Hydropower Pvt.Ltd. |
kathmandu -30, Nepal |
Porposed power House |
nea New Khimti substation |
Survey Lic No: 230 Date: 2072-05-25 |
135 |
Upper Solukhola Hydro Electric 132 kV Transmission Line project |
132 |
11 |
34.5 |
136 |
2077-04-15 |
2102-04-14 |
Beni Hydropower Project Pvt. Ltd. |
Handigaun-5, Kathmandu, Po Box 4691, Phone No:- 4429533 |
Switchyard of upper solu hydro power |
Lamane substation at Tingla |
Survey Lic No: 335 Date: 2074-12-05 |
136 |
Dordi-1 HEP 132 kV Single Circuit Transmission Line |
132 |
3.5 |
12 |
137 |
2077-04-15 |
2102-04-14 |
Dordi Khola Jalbidyut Co. Ltd. |
Kathmandu-11, Tripureshwor; Phone: 01-4232748/49/50; P.O.Box 20290; Email: dordi |
Switchyard of Project |
Kirtipur S/S Lamjung |
Survey Lic No: 339 Date: 2074-12-13 |
137 |
Huxain Cement Malekhu 132kV Transmission Line Project |
132 |
13 |
20 |
138 |
2077-05-17 |
2102-05-16 |
Shree Huxain Cement Narayani Pvt.Ltd. |
Anamnagar,Sahayog Marg-32, Kathmandu; Email: hncement@gmail.com; 01-4430253, 985 |
Dhading NEA Substation |
Huaxain Cement Factory |
Survey Lic No: 396 Date: 2076-02-09 |
138 |
Makari Gad HPP 33 kV Transmission line |
33 |
27.2 |
10 |
139 |
2077-05-31 |
2102-05-30 |
Makarigad Hydropower Pvt. Ltd. |
Kathmandu Metropolitan city, Ward No. 03, Panipokhari |
Switchyard of Makari HPP |
Balanch substation of NEA |
Survey Lic No: 301 Date: 2074-05-14 |
139 |
Tallo Likhu HEP 132kV Transmission Line Project |
132 |
27 |
28.1 |
140 |
2077-06-01 |
2102-05-31 |
Shree Swet Ganga Hydropower and Construction Ltd. |
Naxal, 01-4446442, PO box no. 19737 |
132/11kV Switchyard at Bijulikot(Ramecha |
New Khimti Substation(Ramechap) |
Survey Lic No: 274 Date: 2073-10-03 |
140 |
Surkhet Gangate Matela 33kV transmission Line Project and Substation |
33 |
22 |
3 |
141 |
2077-06-01 |
2102-05-31 |
Nepal Electricity Authority |
Main office,Darbarmarg,Kathmandu |
Ratnlal(Surkhet) |
Matela(Dailekh) |
Survey Lic No: 431 Date: 2076-08-25 |
141 |
Upper Mailung A |
33 |
19 |
6.42 |
142 |
2077-06-22 |
2102-06-21 |
Energy Engineering Limited |
Thapathali-11 Kathmandu, P.O.Box 9292, 01-4101524 |
Switchyard of Project |
Trishuli 3B Hub S/S |
Survey Lic No: 232 Date: 2072-07-12 |
142 |
Likhu-1 Hydropower Project |
132 |
7.5 |
77 |
143 |
2077-07-06 |
2102-07-05 |
Pan Himalaya Energy Pvt.Ltd. |
kathmandu -30, Nepal |
Switchyard of Proposed Power House(Soluk |
Proposed Subsatation of Likhu 2 (Ramecha |
Survey Lic No: 229 Date: 2072-05-07 |
143 |
Dordi Khola Hydropower Project |
132 |
3 |
27 |
144 |
2077-07-19 |
2102-07-18 |
Himalayan Power Partner Ltd. |
Pani Pokhari,Kathmandu |
Swichyard of Dordi Khola HPP |
Udipur NEA HUB |
Survey Lic No: 400 Date: 2076-02-23 |
144 |
Lekhnath Damauli 220 kV Transmission Line Project |
220 |
45 |
600 |
145 |
2077-08-12 |
2102-08-11 |
Nepal Electricity Authority |
Main office,Darbarmarg,Kathmandu |
Lekhanth S/S |
New Damauli S/S |
Survey Lic No: 385 Date: 2075-11-06 Double circuit |
145 |
Balephi Corridor 132 kV TL Project |
132 |
18.167 |
200 |
146 |
2077-08-12 |
2102-08-11 |
Nepal Electricity Authority |
PO box no. 10020, durbar marg |
Balephi S/S at Pantang VDC |
Barahbisey VDC S/S |
Double circuit; Survey Lic No: 293 Date: 2074-04-03 |
146 |
Middle Modi HEP Transmission Line |
132 |
2.5 |
18 |
147 |
2077-11-11 |
2102-11-10 |
Middle Modi Hydro Power Limited |
Chaudhary Group, Sanepa, Lalitpur; Tel No. 01-5521994, 5525039/41 |
Switchyard of Project |
New Modi S/S Kerunga |
Survey Lic No: 464 Date: 2077-05-07 |
147 |
Belchautara Solar Farm TL |
33 |
0.5 |
5 |
148 |
2077-12-03 |
2102-12-02 |
Solar Farm Pvt. Ltd. |
Chandrawati Marga , Ka.Ma.Pa-3 Basundhara, Contact no.: 014370966, 41373662 |
Switchyard of Project |
NEA Khairenitar S/S |
Survey Lic No: 453 Date: 2076-12-03 |
148 |
Upper Richet & Richet HEP Projects Joint Transmission Line |
33 |
14 |
6.98 |
149 |
2077-12-06 |
2102-12-05 |
Shree Richet Jalvidhut Co.Pvt. Ltd. |
Mahalaxmisthan,Lalitpur-15; 01-5527469, 5523784; richethydro@gmail.com |
Switchyard of Upper Richet HEP |
NEA Baseri S/S (Dhading) |
Survey Lic No: 412 Date: 2076-05-17 |
149 |
Ghalemdi khola HEP TL |
33 |
5.2 |
5 |
150 |
2078-01-26 |
2103-01-25 |
Ghalemdi Hydro Limited |
Ka.Ma.Na.Pa-16, Kathmandu Contact No.: 01-5902520 |
Switchyard of HEP |
Dana Substation |
Survey Lic No: 469 Date: 2077-05-24 |
150 |
Upper Syange Khola Small Hydropower Transmission Line Project |
33 |
12 |
2.4 |
151 |
2078-02-03 |
2103-02-02 |
Upper Syange Hydropower Limited, |
Chandol, Kathmandu; 01-4442860, upper.syange@gmail.com |
Switchyard of Upper Syange HEP(Lamjung) |
Khudi NEA Substation(Lamjung) |
Survey Lic No: 321 Date: 2074-10-15 |
151 |
Grid Connected Solar Power Project Dhalkebar 33 kV Transmission Line |
33 |
4.9 |
3 |
152 |
2078-02-18 |
2103-02-17 |
Sagarmatha Energy and Construction Pvt.Ltd. |
Babrmahal,Kathmandu 01-4417898 |
Switchyard of Project (Dhanusha) |
NEA Dhalkebar Substation(Dhanusha) |
Survey Lic No: 447 Date: 2076-09-22 |
152 |
Mai Beni Hydro Power Project Joint Transmission Line |
33 |
14.46 |
22.11 |
153 |
2078-03-01 |
2103-02-31 |
Samling Power Co.Pvt.Ltd. |
Sanepa-2 Lalitpur |
Switchyard of Super Mai A |
NEA Godak S/S |
Survey Lic No: 365 Date: 2075-05-28; Single & Double Circuit |
153 |
Som Radhakrishna Solar Farm's Transmission Line Project |
33 |
13 |
4.4 |
154 |
2078-03-08 |
2103-03-07 |
Nepal Solar Farm Private Limited |
Bafal,Kathmandu-13 |
Switchyard of Project |
NEA Lekhnath Substation |
Survey Lic No: 391 Date: 2076-01-22 |
154 |
Manihiya Sampattiya Cross Boarder Transmission Line Project |
132 |
27.53 |
200 |
155 |
2078-03-24 |
2103-03-23 |
Nepal Electricity Authority |
Main office,Darbarmarg,Kathmandu |
132/33/11 kV Manihiya S/S |
Along 132/33/ kV Nautanhwa(India) S/S AP |
Survey Lic No: 395 Date: 2076-02-07 |
155 |
Chandranigahapur Solar PV 33 kV Transmission Line |
33 |
3 |
4 |
156 |
2078-04-21 |
2103-04-20 |
Api Power Company Limited |
Kathamndi MPC-11 Thapathali; 01-5111093; info@apihydro.com.np |
Switchyard of Project |
NEA Chandranigahapur S/S |
Survey Lic No: 483 Date: 2077-09-08 |
156 |
Upper Chhyangdi Hydropower Project |
33 |
2.35 |
4 |
157 |
2078-05-04 |
2103-05-03 |
Shree Chhyangdi Hydropower Ltd. |
Samta Marga ,Gairidhara-2,Kathmandu |
Switchyard of Upper Chhyangdi HPP(Lamjun |
Switchyard of Chhyangdi HPP |
Survey Lic No: 414 Date: 2076-06-12 |
157 |
New Butwal Bardghat 220 kV Transmission Line Project |
220 |
21 |
500 |
158 |
2078-05-20 |
2103-05-19 |
Nepal Electricity Authority |
Durbar Marg Kathmandu |
Bardghat |
New Butwal S/S |
Survey Lic No: 494 Date: 2078-02-04 |
158 |
Maya Khola HP Transmission Line Project |
33 |
3.4 |
14.9 |
159 |
2078-05-21 |
2103-05-20 |
Maya khola Hydropower Company Pvt.Ltd. |
126 Milap Marg, Bishalnagar,Kathmandu-4 |
Switchyard of Project |
NEA Baneswor Substation |
Survey Lic No: 242 Date: 2072-12-22 |
159 |
Nilgiri Khola 1 & Nilgiri Khola 2 Joint Transmission Line Project |
220 |
7.4 |
109 |
160 |
2078-06-12 |
2103-06-11 |
Nilgiri Khola Hydropower Co. Pvt. Ltd. |
Kamaladi, 01-4169088 |
Switchyard of Nilgiri Khola 1 |
NEA Dana S/S |
Survey Lic No: 300 Date: 2074-05-08 |
160 |
Hiti S/S - Mewa HEP- Middle Mewa HEP 33 kV Transmission Line Project |
33 |
24.73 |
6.5 |
161 |
2078-06-15 |
2103-06-14 |
Mewa Developers Ltd. |
P.O.Box No: 617, Sanepa-2 Lalitpur, 01-5530135,5525228, info@urjadeveloper.com |
NEA Hiti S/S |
Headworks of Middle Mewa HPP site |
Survey Lic No: 476 Date: 2077-06-22 |
161 |
Madhya Tamor Transmission Line Project |
220 |
9 |
358 |
162 |
2078-06-18 |
2103-06-17 |
Sanima Middle Tamor Hydropower Ltd. |
4373030, 4372828 |
Switchyard of Middle Tamor |
NEA Dhungesanghu S/S |
Survey Lic No: 290 Date: 2074-03-07 |
162 |
Chepe Khola Small HP Transmission Line Project |
33 |
20.59 |
8.63 |
163 |
2078-06-19 |
2103-06-18 |
Aashutosh Energy Pvt.Ltd. |
Banasrhali 16 Kathmandu |
Switchyard of Project |
Kirtipur NEA Substaion |
Survey Lic No: 370 Date: 2075-07-07 |
163 |
Gorahi-Madichaur Transmission line |
132 |
36.549 |
150 |
164 |
2078-07-15 |
2103-07-14 |
Nepal Electricity Authority |
Durbarmarg, Kathmandu PO Box No. 10020, Phone No. 01-4153054 |
Madichaur Substation at Subarnawati Rolp |
Ghorahi Substation |
Survey Lic No: 323 Date: 2074-10-18 |
164 |
Grid Connected SPV to Duhabi Transmission Line |
33 |
3 |
6.8 |
165 |
2078-07-26 |
2103-07-25 |
G.I. Solar Private Limited |
Lalitpur Metropolitan-01, Kupandole; 01-5522769, 9851023732 |
Switchyard of Project |
NEA Multifuel Power Plant S/S |
Survey Lic No: 491 Date: 2078-01-19 |
165 |
Borang Naubise (Ratamate) 220/132 kV Transmission Line |
220 |
47.34 |
1936 |
166 |
2078-08-09 |
2103-08-08 |
Nepal Electricity Authority |
Main office,Darbarmarg,Kathmandu |
NEA Borang S/S |
NEA Ratamate,Naubise S/S |
Survey Lic No: 343 Date: 2075-01-07 |
166 |
Sapsup Khola SHP Transmission Line Project |
33 |
2.5 |
6.6 |
167 |
2078-08-22 |
2103-08-21 |
Three Star Hydropower Ltd. |
Madhyapur Thimi-3 Bhaktapur; 01-6635080; sapsu2016@gmail.com |
Switchyard of Project |
NEA Puranagaun Switching Station |
Survey Lic No: 496 Date: 2078-03-22 |
167 |
Upper mailung hydropower transmission line |
132 |
11 |
14.3 |
168 |
2078-09-18 |
2103-09-17 |
Mathillo Mailung Khola Jalbidhyut Company Ltd |
Shankhpark, Dhumbarahi-04, Kathmandu |
Upper mailung switchyard at Champani (Ra |
Trishuli 3B hub substation at Manakamana |
Survey Lic No: 311 Date: 2074-07-14 |
168 |
Upper Machaa Khola HEP 33 kV Transmission Line Project |
33 |
20.57 |
4.55 |
169 |
2078-09-27 |
2103-09-26 |
Bikas Hydropower Company Pvt.Ltd. |
Kathamndu-16 01-4445083/84 |
Switchyard of Upper Machaa Khola Hydropo |
NEA Baseri Substation |
Survey Lic No: 418 Date: 2076-07-05 |
169 |
Kerabari to New Marsyandi 132 kV Transmission Line Project |
132 |
32 |
120 |
170 |
2078-11-02 |
2103-11-01 |
Rastriya Prasaran Grid Company Limited |
DCC Bhawan, Babarmahal Kathmandu; 01-4222693; rpgcl.np@gmail.com |
Kerabari S/S Gorkha |
New Marsyandi Substation Tanhun |
Survey Lic No: 392 Date: 2076-01-22 |
170 |
Mewa to Change 132 kV Tr.Ln. in Taplejung District |
132 |
20 |
154.35 |
171 |
2078-11-02 |
2103-11-01 |
Rastriya Prasaran Grid Company Limited |
Babarmahal, Kahmandu; Tel:01-4266693, P.B.No. 19752; Email info@rpgcl.com |
Mewa Substation |
Change Sub-station |
Survey Lic No: 355 Date: 2075-03-27 |
171 |
Tranmission Line for Kabeli B-1 Cascade HEP |
33 |
3 |
9.94 |
172 |
2078-11-12 |
2103-11-11 |
Arun Valley Hydropower Development Company Ltd. |
GPO Box: 11039, Thapathali, KTM; 01-5111086;arunvalley2054@gmail.com |
Switchyard of Project |
Kabeli B-1 HEP Pooling S/S |
Survey Lic No: 502 Date: 2078-05-04 |
172 |
Lower Tadi Khola Transmission Line Project |
33 |
3 |
4.993 |
173 |
2078-11-20 |
2103-11-19 |
Buddha Bhumi Nepal Hydro Power Co . Ltd. |
Panipokhari Maharajgunj-03, KTM, 01-4003050; lowertadi@gmail.com |
Switchyard of Project |
NEA Samundratar S/S |
Survey Lic No: 516 Date: 2078-08-20 |
173 |
Siddhi Khola 33kV Transmission Line Project |
33 |
16 |
10 |
174 |
2078-11-23 |
2103-11-22 |
Siddhi Hydropower company Pvt. Ltd |
Lalitpur, Nepal: 01-5011841 |
Swichyard of project |
NEA Fikkal Substation |
Survey Lic No: 265 Date: 2073-08-10 |
174 |
Sitalpati to Tumlingtar Sankhuwasava District |
220 |
13.615 |
600 |
175 |
2078-12-24 |
2103-12-23 |
Nepal Electricity Authority |
Main office,Darbarmarg,Kathmandu |
Sitalpati Substation |
Tumlingtar Substation |
Survey Lic No: 368 Date: 2075-06-14 |
175 |
Nupche Khola Hydropower Project |
132 |
24 |
57.5 |
176 |
2078-12-28 |
2103-12-27 |
Vision Energy and power Pvt.Ltd. |
New Baneshwor ,Kathmandu ,Nepal |
Switchyard of Nupche Khola HEP |
NEA Garjyang Substation |
Survey Lic No: 341 Date: 2074-12-15 |
176 |
Upper Gaddi Gad HEP 33 kV Transmission Line Project |
33 |
0.3 |
1.55 |
177 |
2079-01-26 |
2104-01-25 |
Shaileshwori Power Nepal Pvt. Ltd. |
Sukedhara -04, Kathmandu |
Switchyard of Project |
Sana Gaoun S/S Doti |
Survey Lic No: 488 Date: 2077-11-02 |
177 |
Kaligandaki Ridi 132 kV Transmission Line |
132 |
22.45 |
230 |
178 |
2079-01-26 |
2104-01-25 |
Nepal Electricity Authority |
Main office,Darbarmarg,Kathmandu |
Switchyard of Kaligandaki Substation |
NEA Proposed Ridi Substation |
Survey Lic No: 401 Date: 2076-02-23 |
178 |
Dhalkebar Balganga Transmission Line Project |
132 |
23.99 |
230 |
179 |
2079-01-29 |
2104-01-28 |
Nepal Electricity Authority |
Main office,Darbarmarg,Kathmandu |
Dhalkebar -Loharpatti Tower No.13 |
Proposed NEA Balganga Substation |
Survey Lic No: 404 Date: 2076-03-12 |
179 |
Super Madi HPP 132 kV Transmission Line Project |
132 |
19.5 |
68 |
180 |
2079-03-07 |
2104-03-06 |
Super Madi Hydro Power Limited |
Dillibazar,Kathmandu |
Switchyard of Super Madi HPP |
NEA Lekhnath Substation |
Survey Lic No: 369 Date: 2075-06-15 |
180 |
Ghar Khola HEP 33kV Transmission Line Project |
33 |
7 |
14 |
181 |
2079-03-12 |
2104-03-11 |
Shree Myagdi Hydropower Limited |
Baluwatar-3,Kathmandu |
Switchyard of Ghar khola HPP |
NEA Dana Substation |
Survey Lic No: 390 Date: 2075-12-03 |
181 |
Bhumahi Hakoi 132kV Transmission Line Project |
132 |
14.36 |
200 |
182 |
2079-03-13 |
2104-03-12 |
Nepal Electricity Authority |
Main office,Darbarmarg,Kathmandu |
Sunwal Substaion |
Proposed Hakoi Subsation |
Survey Lic No: 437 Date: 2076-09-04 |
182 |
Ratodhunga Upper Myagdi 1 Construction Power Transmission Line Project |
33 |
18.5 |
4 |
183 |
2079-03-13 |
2104-03-12 |
Upper Myagdi Hydropower Pvt. Ltd. |
Kamaladi-28, Kathmandu; 01-5530135, info@urjadeveloper.com |
NEA Ratodhunga S/S |
Headwork's of Upper Myagdi 1 HEP |
Survey Lic No: 498 Date: 2078-04-07 |
183 |
Transmission Line for Upper Chameliya HEP |
132 |
16 |
40 |
184 |
2079-04-09 |
2104-04-08 |
Api Power Company Limited |
Trade Tower Nepal Thapathali, Kathmandu-11; 01-5111093 |
Switchyard of Project |
NEA Balach S/S |
Survey Lic No: 533 Date: 2078-12-07 |
184 |
Grid Connected Pratappur SPV Joint Transmission Line Project |
33 |
3.768 |
15 |
185 |
2079-04-10 |
2104-04-09 |
National Solar Power Company Pvt. Ltd. |
Jawalakhel -13 Lalitpur; 01-5275070 |
Switchyard of Project |
NEA Gandak S/S |
Survey Lic No: 525 Date: 2078-10-07 |
185 |
Transmission Line for Puwa 2 HEP |
33 |
5 |
4.96 |
186 |
2079-04-12 |
2104-04-11 |
People's Power Limited |
Kamal Pokhari Kathmandu; 01-4437611 |
Switchyard of Project |
Switchyard of Upper Puwa 1 HEP |
Survey Lic No: 521 Date: 2078-08-28 |
186 |
Upper Midim Hydropower Transmission Line Project |
33 |
26.13 |
7.5 |
187 |
2079-04-30 |
2104-04-29 |
Bhujung Hydropower Pvt.Ltd. |
Devkota Sadak-40781,Mid Baneshwor,Kathmandu-34 |
Swithchyard of Project (Lamjung) |
NEA Bhorletar Subsation |
Survey Lic No: 436 Date: 2076-08-30 |
187 |
Mid Solu Khola HPP 132 kV Transmission Line Project |
132 |
0.55 |
9.5 |
188 |
2079-05-08 |
2104-05-07 |
Mid Solu Hydropower Company Pvt. Ltd. |
Kathmandu-31 Balbhadra Marg, 9851105341; midsole.hydropower@gmail.com |
Switchyard of Project |
LILO at AP 20 of USK TL |
Survey Lic No: 504 Date: 2078-05-18 |
188 |
Upper Fhawa Khola HPP 33 kV Transmission Line |
33 |
7.2 |
5.8 |
189 |
2079-05-16 |
2104-05-15 |
Unitech Hydropower Company Pvt. Ltd. |
Mid Baneshwor, Kthmandu-31; 01-4106123, unitechhydropower@gmail.com |
Switchyard of Project |
NEA Kabeli S/S Amarpur |
Survey Lic No: 474 Date: 2077-06-22 |
189 |
Madhya Mewa Dhunge Sangu 132 kV Transmission Line Project |
132 |
10.7 |
73.5 |
190 |
2079-05-26 |
2104-05-25 |
Shree Mewa Developers Pvt. Ltd. |
Tripureshwor,Kathmandu |
Switchyard of Madhya Mewa Hydro Power Pr |
Dhunge Sangu NEA Substation |
Survey Lic No: 358 Date: 2075-04-29 |
190 |
Phukot- Betan 400 kV Transmission Line Project |
400 |
54 |
2500 |
191 |
2079-05-31 |
2104-05-30 |
Rastriye Prasaran Grid Company Limited |
Babarmahal, Kathmandu; 01-4266693; rpgcl.np@gmail.com |
Proposed Phukot S/S |
Proposed Betan S/S |
Survey Lic No: 461 Date: 2077-04-28 |
191 |
Betan to Dododhara 400 kV Transmission Line Project |
400 |
37 |
2647 |
192 |
2079-05-31 |
2104-05-30 |
Rastriya Prasaran Grid Company Limited |
B.P.C Complex,Budhnagar,Kahmandu |
Proposed Betan S/S |
Proposed Dododhara S/S |
Survey Lic No: 406 Date: 2076-03-27 |
192 |
Dododhara to Karmadev (Indo-Nepal boarder) 400 kV Transmission line |
400 |
30 |
2500 |
193 |
2079-05-31 |
2104-05-30 |
Rastriya Prasaran Grid Company Limited |
Buddhanagar, Kathmandu |
Proposed Dododhara S/S |
Karmadev Nepal-India boarder |
Survey Lic No: 305 Date: 2074-05-28 |
193 |
Amarpur-Dhungesangu 132 kV Transmission Line Project |
132 |
19.13 |
200 |
194 |
2079-06-04 |
2104-06-03 |
Nepal Electricity Authority |
Main office,Darbarmarg,Kathmandu |
Amarpur Substation |
Dhungesangu Substation |
Survey Lic No: 397 Date: 2076-02-15 |
194 |
Godak Soyak Transmission Line Project |
132 |
6.56 |
200 |
195 |
2079-06-04 |
2104-06-03 |
Nepal Electricity Authority |
Durbarmanrga Kathmandu, |
NEA Godak S/S |
Kabeli Corridor at Soyak |
Survey Lic No: 455 Date: 2077-01-30 |
195 |
Surkhet Dailekh 132kV Transmission Line Project |
132 |
32.05 |
200 |
196 |
2079-07-18 |
2104-07-17 |
Nepal Electricity Authority |
Main office,Darbarmarg,Kathmandu |
Surkhet NEA Substation (Surkhet) |
Dailekh NEA Substation (Dailekh) |
Survey Lic No: 425 Date: 2076-08-19 |
196 |
Lalbandi Salempur 132kV Transmission Line |
132 |
19.85 |
200 |
197 |
2079-07-18 |
2104-07-17 |
Nepal Electricity Authority |
Main office,Darbarmarg,Kathmandu |
NEA Nawalpur Substation |
Proposed Salempur Substation |
Survey Lic No: 398 Date: 2076-02-15 |
197 |
Seti Nadi HEP 132 kV Transmission Line Project |
132 |
3.687 |
84.595 |
198 |
2079-07-21 |
2104-07-20 |
Vision Lumbini Urja Company Ltd |
Butwal-06, Gurudwapath. Buddhnagar 10, KTM, 01-5902560, 071-544316 |
Switchyard of Seti Nadi roject |
NEA Lahacowk S/S |
Survey Lic No: 538 Date: 2079-01-07 |
198 |
Trishuli 3B to Kalikasthan Transmission Line Project |
33 |
5 |
8 |
199 |
2079-07-29 |
2104-07-28 |
Nepal Electricity Authority |
Durbar Marg, Kathmandu 01-4153007 |
Proposed Trishuli 3B S/S |
Proposed Kalikasthan S/S |
Survey Lic No: 545 Date: 2079-01-26 |
199 |
Jhapa Solar PV Transmission Line Project |
33 |
0.7 |
10 |
200 |
2079-08-08 |
2104-08-07 |
Jhapa Energy Limited |
Birtamod-4, Jhapa |
Switchyard of Project |
NEA Buluchowk S/S |
Survey Lic No: 520 Date: 2078-08-28 |
200 |
Sanjen Khola Hydroelectric Project 132 kV Transmission line |
132 |
7.5 |
78 |
201 |
2079-08-20 |
2104-08-19 |
Salasungi Power Pvt. Limited |
Sanepa, Lalitpur, Tel:- +977-1-5551248, 5535818 |
Switchyard of Sanjen Khola HP |
NEA Chilime Hub S/S |
Survey Lic No: 303 Date: 2074-05-19 |
201 |
Doodhpokhari Chepe & Super Chepe HEP Joint Transmission Line |
33 |
24 |
17.886 |
202 |
2079-09-29 |
2104-09-28 |
Doodhpokhari Chepe Hydropower Pvt. Ltd. |
Kathmandu-10; 9851153723 |
Switchyard of Project |
NEA Kirtipur S/S |
Survey Lic No: 490 Date: 2077-11-11 |
202 |
Upper Piluwa Khola-2 HEP 33 kV Transmission Line |
33 |
12 |
12.42 |
203 |
2079-10-04 |
2104-10-03 |
Menchhiyam Hydropower Pvt. Ltd. |
Lainchour, Kathmandu; 01-4440706,4440465;9851020604; menchhiyam@gmail.com |
Switchyard of Project |
Baneshwor Substation of NEA |
Survey Lic No: 470 Date: 2077-05-31 |
203 |
Lower Selang Hydro power Joint Transmission Line Project |
33 |
14 |
3.435 |
204 |
2079-10-24 |
2104-10-23 |
Sewa Hydro Limited, |
Lalitpur-10, Jwagal, sewahydrolimited@gmail.com; 01-5260699 |
Switchyard of Lower Selang Project |
NEA Chautara S/S |
Survey Lic No: 563 Date: 2079-05-22 |
204 |
Namarjun Madi Hydro Power Project |
132 |
4.6 |
12 |
205 |
2079-10-24 |
2104-10-23 |
Himalayan Hydro Power Ltd. |
Budhnagar ,Kathmandu,9843176324,9751076999 |
Switchyard of Namarjun Madi Hydro Power |
Switchyard of Upper Madi Hydropower Proj |
Survey Lic No: 377 Date: 2075-09-20 |
205 |
Yambaling HPP Transmission Line Project |
33 |
7 |
7.27 |
206 |
2079-10-24 |
2104-10-23 |
Yambaling Hydropower Ltd. |
Jwagal-10, Lalitpur 015550934 |
Switchyard of Project |
Switchyard of Upper Balephi A |
Survey Lic No: 539 Date: 2079-01-08 |
206 |
Grid Connected SPV (Block 1 & Block 2) Banke Joint Transmission |
33 |
15 |
20 |
207 |
2079-11-29 |
2104-11-28 |
Pure Energy Pvt. Ltd. |
Hyatt Palace, Kathmandu-13; 9801063049, sunita.kc@golyangroup.com |
Switchyard of Project |
NEA Kohalpur S/S |
Survey Lic No: 503 Date: 2078-05-04 |
207 |
Bhaktpur-Thimi 132 kV Under Ground Transmission Line Project |
132 |
3.27 |
280 |
208 |
2079-12-01 |
2104-11-30 |
Nepal Electricity Authority |
Main office,Darbarmarg,Kathmandu |
Bhaktpur 132kV Substation |
Proposed Thimi Substation |
Survey Lic No: 405 Date: 2076-03-20 |
208 |
Super Kabeli Khola A, Super Kbeli Khola Cascade & Kabeli-3 HEP Joint Transmissi |
132 |
30.35 |
47.43 |
209 |
2079-12-09 |
2104-12-08 |
Snow Rivers Pvt. Ltd. |
GPO Box: 20762 Lazimpat Kathamndu-2 Nepal, 9851220305 |
Switchyard of Kabeli Khola A Project |
NEA Amarpur S/S |
Survey Lic No: 522 Date: 2078-09-02 |
209 |
Kohalpur Nepalgunj 132kV ransmission Line Project |
132 |
11 |
200 |
210 |
2079-12-23 |
2104-12-22 |
Nepal Electricity Authority |
Main office,Darbarmarg,Kathmandu |
NEA Kohalpur Substation |
NEA Proposed Janaki Substation |
Survey Lic No: 429 Date: 2076-08-19 |
210 |
Parwanipur Pokhariya 132 kV Transmission Line Project |
132 |
20 |
250 |
211 |
2079-12-28 |
2104-12-27 |
Nepal Electricity Authority |
Durbar Marg, Kathmandu 01-4153007 |
NEA Parwanipur S/S |
Proposed Pokhariya S/S |
Survey Lic No: 512 Date: 2078-08-14 |
211 |
Rupani Bodebarsain 132 kV Transmission Line Project |
132 |
18.605 |
200 |
212 |
2079-12-29 |
2104-12-28 |
Nepal Electricity Authority |
Main office,Darbarmarg,Kathmandu |
NEA Rupani S/S |
Proposed Bodebarsain S/S |
Survey Lic No: 430 Date: 2076-08-19 |
212 |
Down Piluwa Khola 33 kV Transmission Line Project |
33 |
3.34 |
10.3 |
213 |
2080-02-29 |
2105-02-28 |
Rver Falls Power Limited |
Kathmandu-28, Kamaladi, 01-5902330 |
Switchyard of Project |
NEA Baneshwor S/S |
Survey Lic No: 582 Date: 2079-10-26 |
213 |
Koshi Corridor 220kV T. L. Dharan Sub Station Project |
220 |
0.6 |
100 |
214 |
2080-02-29 |
2105-02-28 |
Nepal Electricity Authority |
Durbar Marg Kathmandu |
AP 57/2 of Koshi Corridor |
AP 57/2 of Koshi Corridor |
Survey Lic No: 492 Date: 2078-01-24 |
214 |
Bhim khola Hydro Power Project Baglung District |
33 |
7 |
4.96 |
215 |
2080-02-32 |
2105-02-31 |
Shikhar Power Development Limited |
Baneshwor,Kahmandu Contact No. 9851133303 |
Bhim Khola Hydro Power Project |
NEA Burtiwang Substation |
Survey Lic No: 359 Date: 2075-04-29 |
215 |
Sangu Khola Hydro Power Project |
132 |
7.4 |
30.5 |
216 |
2080-04-11 |
2105-04-10 |
Him Parvat Hydro Power Pvt .Ltd. |
Tripureshwor,Kathmandu |
Sangu Khola Hydro Power Project |
Singati Substation |
Survey Lic No: 348 Date: 2075-03-12 |
216 |
Upper Chirkhwa Hydropower Transmission Line Project |
33 |
19.4 |
22.91 |
217 |
2080-04-11 |
2105-04-10 |
Chirkhwa Hydropower Ltd. |
Koteshwor,Kathmandu-32 |
Switchyard of Project (Bhojpur) |
Tumlingtar Substation(Sankhuwasabha) |
Survey Lic No: 435 Date: 2076-08-30 |
217 |
Liping Khola HEP Transmission Line Project |
132 |
14 |
16.26 |
218 |
2080-04-16 |
2105-04-15 |
Him River Power Pvt. Ltd. |
Narayanchaur, Naxal, KTM; 01-4441535 |
Switchyard of Project |
Upper Chaku HEP Swithyard |
Survey Lic No: 540 Date: 2079-01-08 |
218 |
Upper Ingwa Transmission Line Project |
33 |
16 |
9.7 |
219 |
2080-05-12 |
2105-05-11 |
Ingwa Hydro Power Ltd, |
Trade Tower Thapathali-11; KTM; 01-5111093 |
Switchyard of Project |
NEA Amarpur S/S |
Survey Lic No: 517 Date: 2078-08-20 |
219 |
Mathillo Suri Khola Hydro Power Transmission Line Project |
33 |
4.3 |
7 |
220 |
2080-05-22 |
2105-05-21 |
Shree Makar Jitumaya Hydro Power Pvt.Ltd. |
Tripureshwor,Kathmandu |
Switchyard of Mathillo Suri Khola Hydro |
Switchyard of Suri Khola Hydro Power Pro |
Survey Lic No: 349 Date: 2075-03-12 |
220 |
Sangu khola-1 Hydro Power Project |
33 |
5.83 |
5.5 |
221 |
2080-07-22 |
2105-07-21 |
Him Parbat Hydropower Pvt. Ltd. |
Tripureshwor, Kathmandu, Phone:- 4117008 |
Switchyard of Sangu khola-1 Hydro Powe |
Switchyard of Sangu khola Hydro Power Pr |
Survey Lic No: 350 Date: 2075-03-17 |
221 |
Chobar Patan 132 kV Transmission Line Project |
132 |
4.5 |
300 |
222 |
2080-08-12 |
2105-08-11 |
Nepal Electricity Authority |
Durbar Marg, Kathmandu 01-4153007 |
Chobar S/S |
Patan S/S |
Survey Lic No: 528 Date: 2078-11-06 |
222 |
Chandrapur Sukdev Chowk 132kV Transmission Line Project |
132 |
36 |
200 |
223 |
2080-08-19 |
2105-08-18 |
Nepal Electricity Authority |
Main office,Darbarmarg,Kathmandu |
NEA ChandrpurSubstation |
Proposed NEA Substation at Saruatha |
Survey Lic No: 423 Date: 2076-08-16 |
223 |
Upper Piluwa 3 HPP Transmission Line |
33 |
14 |
4.95 |
224 |
2080-09-02 |
2105-09-01 |
Mabilung Energy Ltd. |
Lalitpur-10, Mobile: 9841509412; Email: mabilung@gmail.com |
Switchyard of Project |
NEA Baneshwar S/S Sankhuwasabha |
Survey Lic No: 465 Date: 2077-05-07 |
224 |
Lower Erkhuwa Khola Transmission Line Project |
33 |
3.1 |
14.15 |
225 |
2080-09-08 |
2105-09-07 |
Lower Erkhuwa Hydropower Co. Pvt. Ltd. |
Binayak Nagar, KTM-10; 015172683/85 |
Switchyard of Lower ErkhuwaProject |
Switchyard of Chirkhuwa HEP |
Survey Lic No: 552 Date: 2079-03-06 |
225 |
Rele khola Transmission Line Project |
33 |
4.23 |
6 |
226 |
2080-10-14 |
2105-10-13 |
Him Consult Pvt.Ltd. |
sahavagita marg 10 ,kathmandu,nepal |
Switchyard of Rele khola HEP |
Dana substation |
Survey Lic No: 351 Date: 2075-03-12 |
226 |
Bafikot- Khungri 132 kV Transmission Line |
132 |
75 |
200 |
227 |
2080-10-14 |
2105-10-13 |
Nepal Electricity Authority |
Durbarmarg, Kathmandu |
Uttarganga Hub Substation at Banphikot, |
Proposed Khungri Substation at Khungri |
Survey Lic No: 600 Date: 2080-03-07 |
227 |
Junbesi Khola HPP Transmission Line Project |
33 |
6 |
5.2 |
228 |
2080-10-16 |
2105-10-15 |
Dovan Hydropower Pvt. Ltd. |
Min Bhawan, New baneshwor KTM; 01-6214401, dovanhydropp@gmail.com |
Switchyard of Project |
Switchyard of Upper Solukhola HEP |
Survey Lic No: 510 Date: 2078-07-22 |
228 |
Thulo Khola HPP 220 kVTransmission Line Project |
220 |
8.4 |
21.3 |
229 |
2080-11-03 |
2105-11-02 |
Samyukta Urja Private Limited |
Kupandole, Lalitpur; 9841599452 |
Switchyard of Thulo Khola HPP |
220 kVSwitchyard of Rahughat Mangle HPP |
Survey Lic No: 553 Date: 2079-03-07 |
229 |
New Butwal Lamahi Transmission Line |
400 |
160.8 |
4000 |
230 |
2080-11-27 |
2105-11-26 |
Nepal Electricity Authority |
Durbarmarga Kathmandu |
New Butwal Substation |
Lamahi Substation |
Survey Lic No: 457 Date: 2077-04-12 |
230 |
Arun Corridor (Haitar- Sitalpati) 400 kV Transmission Line Project |
400 |
35 |
4400 |
231 |
2080-11-30 |
2105-11-29 |
Rastriya Prasaran Grid Company Ltd |
DCC Bhawan Babarmahal, Kathmandu; 01-4222693; rpgcl.np@gmail.com |
Haitar S/S |
Sitalpati S/S |
Survey Lic No: 332 Date: 2074-12-01 |
231 |
Lower Modi New Modi 132 kV Transmission Line Project |
132 |
8.51 |
200 |
232 |
2080-12-12 |
2105-12-11 |
Nepal Electricity Authority |
Durbar Marg, Kathmandu 01-4153007 |
Lower Modi S/S |
New Modi S/S |
Survey Lic No: 551 Date: 2079-03-06 |
232 |
Prasauni Birgaunj 132 kV Underground Transmission Line |
132 |
3.2 |
300 |
233 |
2080-12-12 |
2105-12-11 |
Nepal Electricity Authority |
Durbar Marg, Kathmandu 01-4153007 |
Proposed Prasauni S/S |
NEA Birgunj (Gandak) S/S |
Survey Lic No: 537 Date: 2079-01-07 |
233 |
Luja Kola & Rauje Khola- Tingla Transmission Line Project |
132 |
32.84 |
42.88 |
234 |
2080-12-28 |
2105-12-27 |
Silk Power Pvt. Ltd. |
Madhyapur Thimi-3, Bhaktapur; 9841018543 |
Switchyard of Luja Khola Project |
NEA Tingla S/S |
Survey Lic No: 524 Date: 2078-09-27 |
234 |
Dudhkund Khola Tingala Transmission Line Project |
33 |
24.58 |
12 |
235 |
2081-01-20 |
2106-01-19 |
Mount Everest Power Development Pvt. Ltd. |
Lalitpur Metropolitan-15, Mahalaxmisthan; 01-5527469, mounteverestpower@gmail.co |
Switchyard of Project |
NEA Tingla S/S |
Survey Lic No: 505 Date: 2078-05-27 |
235 |
Madame Khola - Super Madi Transmission Line Project |
132 |
13.43 |
24 |
236 |
2081-01-21 |
2106-01-20 |
Madame Khola Hydropower Pvt. Ltd. |
Devkota Sadak-40781, Mid Baneshwor, Kathmandu-34; 01-4480564; info@madamehydro.c |
Switchyard of Project |
Switchyard of Super Madi HPP |
Survey Lic No: 466 Date: 2077-05-17 |
236 |
Seti Khola 33 kV Transmission Line Project |
33 |
12.27 |
3.5 |
237 |
2081-01-28 |
2106-01-27 |
Parbat Painya Khola Hydropower Company Pvt. Ltd. |
Tokha-05, Dhapasi, Kathmandu 01-4365425 |
Switchyard of Project |
NEA, Lankhu S/S |
Survey Lic No: 579 Date: 2079-10-04 |
237 |
Tamakoshi V HEP 220 kV Transmission Line Project |
220 |
3.4 |
577.8 |
238 |
2081-02-09 |
2106-02-08 |
Tamakoshi Jalvidhyut Company Ltd. |
Oharboat Marg Thapagaoun , New Baneshowr; 01-4245061/63/67, tamakoshi5@nea.org.n |
Tower No. 17 of UTKCL TL |
Tower No. 18 of UTKCL TL |
Survey Lic No: 481 Date: 2077-08-26 |
238 |
Buku Khola Garjyang 33 kV Transmission Line Project |
33 |
18.725 |
6 |
239 |
2081-02-17 |
2106-02-16 |
Appolo Hydropower Ltd. |
Nagpokhari Kathmandu |
Switchyard of Project |
NEA Garjyang Substation |
Survey Lic No: 576 Date: 2079-09-08 |
239 |
Chepe A HEP transmission Line Project |
33 |
4.28 |
7 |
240 |
2081-03-02 |
2106-03-01 |
Champawati Hydro Power Ltd. |
Nagarjun-1, Raniban, Kathmandu |
Switchyard of Project |
Parajuli Gaun LILO Switching S/S |
Survey Lic No: 627 Date: 2080-12-08 |
240 |
Mewa Khola Hydro Power Transmission Line Project |
132 |
7.08 |
50 |
241 |
2081-03-04 |
2106-03-03 |
United Mewa Khola Hydro Power Pvt.Ltd. |
Dillibazar -29,Kathmandu |
Mewa Khola Hydro Power Project Switchyar |
Dhungesangu NEA Substation |
Survey Lic No: 378 Date: 2075-09-23 |
241 |
Lankhuwa Khola Sana HPP - Tumlingtar S/S 33 kV Transmission Line Project |
33 |
19 |
5 |
242 |
2081-03-04 |
2106-03-03 |
Sabhapokhari Hydro Power Ltd. |
Bansathali Kathmandu 01-4390229 |
Switchyard of Project |
NEA Tumlingtar S/S |
Survey Lic No: 575 Date: 2079-09-18 |
242 |
Lahan Sukhipur 132kV Transmission Line Project |
132 |
16.136 |
200 |
243 |
2081-03-07 |
2106-03-06 |
Nepal Electricity Authority |
Main office,Darbarmarg,Kathmandu |
Lahan NEA Substation(Siraha) |
Proposed Sukhipur NEA Substation(Siraha) |
Survey Lic No: 428 Date: 2076-08-19 |
243 |
Khimti-2 HEP - Garjyang- New Khimti Tower Number AP26-27 132 kV transmission lin |
132 |
1.81 |
48.8 |
244 |
2081-03-07 |
2106-03-06 |
Peoples Energy Limited |
Shree Krishna Sadan, New Baneshwor-10, Kathmandu, Phone:- +977-1-4781891, 478603 |
Khimti-2 Powerhouse/switchyard |
NEA Garjyang- New Khimti Tower Number AP |
Survey Lic No: 554 Date: 2079-03-13 |
244 |
Dailekh-Kalikot-Jumla 132 kV Transmission Line and Substation Project |
132 |
82.14 |
238 |
245 |
2081-03-14 |
2106-03-13 |
Nepal Electricity Authority |
Main office,Darbarmarg,Kathmandu |
Dailekh Substation |
Jumla Substation |
Survey Lic No: 444 Date: 2076-09-16 |
245 |
Lower Indrawati 66 kV Transmission Line project |
66 |
0.21104 |
12 |
246 |
2081-03-25 |
2106-03-24 |
National Hydro Power Co. Ltd. |
New Baneshwor-10 KTM, 01-5172683; info@nhpc.com |
Switchyard of Project |
Existing 66 kV TL of Indrawati-III (LIL |
Survey Lic No: 580 Date: 2079-10-09 |
246 |
Suni Gad HEP 33 kV Transmission Line Project |
33 |
9.46 |
11.05 |
247 |
2081-04-08 |
2106-04-07 |
Omega Energy Developer Pvt. Ltd. |
Kathmandu-04, Chandole, 01-4529044 |
Switchyard of Project |
NEA Chainpur S/S |
Survey Lic No: 613 Date: 2080-06-26 |
247 |
Langtang Khola Swichyard to Chilime Hub Transmission Line Project |
132 |
3.876 |
20 |
248 |
2081-04-15 |
2106-04-14 |
Multi Energy Development Pvt. Ltd. |
GPO Box:10242 Kathamndu 01-4781891; langtangkhola@gmail.com |
Switchyard of Project |
NEA Chilime Hub S/S |
Survey Lic No: 542 Date: 2079-01-11 |
248 |
Galchhi Ratamate 220 kV Transmission Line Project |
220 |
8.5 |
1147 |
249 |
2081-04-18 |
2106-04-17 |
Nepal Electricity Authority |
Durbar Marg, Kathmandu 01-4153007 |
Galchhi |
NEA Ratamate,Naubise S/S |
Survey Lic No: 549 Date: 2079-02-17 |
249 |
Rasuwa Bhotekoshi HEP TL Project |
220 |
3.608 |
120 |
250 |
2081-04-32 |
2106-04-31 |
Langtang Bhotekoshi Hydropower Company Pvt. Ltd. |
01-4440706 |
Respective Switchyard of the project |
Chilime Hub at Chilime VDC, Rasuwa |
Survey Lic No: 298 Date: 2074-04-29 |
250 |
Super Hewa khola- Baneswor 33 kV Transmission Line Project |
33 |
14.07 |
6 |
251 |
2081-05-06 |
2106-05-05 |
Super Hewa Power Company Ltd. |
Anamnagar, Kathmandu; 01-4388307,4388299; superhewapc@gmail.com |
Switchyard of Project |
NEA Baneshwor S/S |
Survey Lic No: 535 Date: 2078-12-07 |
251 |
Betan Karnali HEP 400 kV Transmission Line Project |
400 |
5 |
439 |
252 |
2081-06-06 |
2106-06-05 |
Betan Karnali Snchayakarta Hydropower Co.Ltd. |
Durbarmarg Kathmandu; 01-4244903, E-mail: info@bkshcl.com.np |
Respective Switchyard of the Project |
Baghmara S/S Betan Hub Surkhet |
Survey Lic No: 471 Date: 2077-06-04 |
252 |
Upper Thulo Khola A HPP 132 kV Transmission Line Project |
132 |
16 |
22.5 |
253 |
2081-07-02 |
2106-07-01 |
Thulo Khola Hydropoer Ltd. |
Mid Baneshwor-31, Kathmandu; 01-5321777 |
Switchyard of Project |
NEA Dana S/S |
Survey Lic No: 544 Date: 2079-01-26 |
253 |
Buku Kapati 33 kV Transmission line Project |
33 |
10.9 |
5 |
254 |
2081-07-07 |
2106-07-06 |
Him Star Urja Company Ltd. |
Tusal, Kathmandu-7; 9851105711 |
Switchyard of Project |
NEA Bamti S/S |
Survey Lic No: 577 Date: 2079-10-04 |
254 |
33 kV Transmission Line for Dharamnagar Solar Farm |
33 |
3.3 |
25 |
255 |
2081-07-25 |
2106-07-24 |
Pashupati Renewables Pvt. Ltd. |
36 Macchapucchre Marg, Gyaneshwar, Kathmandu, Phone No. 9801025634 |
Dharamnagar Solar Farm switchyard |
NEA Chaunata Substation |
Survey Lic No: 546 Date: 2079-02-05 |
255 |
Super Nyadi 132 kV Transmission Line Project |
132 |
5.5 |
42.6 |
256 |
2081-08-07 |
2106-08-06 |
Siuri Nyadi Power Ltd. |
Hanumanstan, Anamnagar, Kathmandu,01-5705159 |
Switchyard of Project |
Switchyard of Nyadi HEP |
Survey Lic No: 557 Date: 2079-04-11 |
256 |
Jeera Bhawani Sedwa Solar Plant Transmission Line |
33 |
3.5 |
10 |
257 |
2081-08-10 |
2106-08-09 |
Tarai Solar Pvt. Ltd. |
Gahanapokhari, KTM-05; 01-4419321 |
Switchyard of Project |
NEA Sedwa S/S |
Survey Lic No: 606 Date: 2080-04-08 |
257 |
Upper Modi A and Upper Modi HEP 132 kV Transmission Line |
132 |
11.5 |
60.2 |
258 |
2081-10-07 |
2106-10-06 |
Modi Jalvidyut Company Limited |
United World Trade Centre, Tripureshwor; 01-4117167, uppermodi42@nea.org.np |
Switchyard of Upper Modi A HEP |
New Modi S/S |
Survey Lic No: 480 Date: 2077-08-26 |
258 |
Hidi Khola Transmission Line Project |
33 |
10.176 |
6.82 |
259 |
2081-11-02 |
2106-11-01 |
White Lotus Power Ltd. |
New Baneshwor -10, Kathmandu, 01-4785660 |
Switchyard of Project |
Switchyard of Nyadi HEP |
Survey Lic No: 565 Date: 2079-06-12; Single Ckt |
259 |
Upper Lohore Khola Hydropower Company Ltd. |
33 |
2.8 |
4 |
260 |
2081-11-06 |
2106-11-05 |
Upper Lohore Khola Hydropower Company Ltd. |
Kathmandu |
Respective Switchyard of the project |
Switchyard of Padam Khola HPP |
Survey Lic No: 670 Date: 2081-07-05 |
260 |
Palpa Substation and Transmission Line Project |
220 |
0.635 |
1000 |
261 |
2081-11-13 |
2106-11-12 |
Nepal Electricity Authority |
Durbar Marg, Kathmandu 01-4153007 |
LILO@Kusma New Butwal TL |
LILO@Kaligandkai Butwal TL |
Survey Lic No: 566 Date: 2079-06-23;Double ckt |
261 |
Tamor Dhungesanghu 220 kV Transmission Line |
220 |
32 |
700 |
262 |
2081-11-21 |
2106-11-20 |
Rastriya Prasaran Grid Company Limited |
DCC Bhawan Babarmahal, Kathmandu; 01-4266693; rpgcl.np@gmail.com |
Proposed Tamor S/S |
Proposed Dhungesanghu S/S |
Survey Lic No: 485 Date: 2077-09-22,Double ckt |
262 |
Upper Khudi Hydropower Project |
132 |
5 |
26 |
263 |
2081-12-05 |
2106-12-04 |
Super Khudi Hydropower Pvt.Ltd. |
Charkhal,Dillibazzar,Kathmandu,Nepal 01-4424644 4424655 4434003 |
Swichyard of Upper Khudi HPP(Lamjung) |
Khudi(Tarikuna) NEA Substation(Lamjung) |
Survey Lic No: 427 Date: 2076-08-19 |
263 |
Sabha Khola B to Sitalpati 132 kV Transmission Line Project |
132 |
22.738 |
42.15 |
264 |
2081-12-12 |
2106-12-11 |
Orbit Energy Limited |
Handigaun,kathmandu |
Switchyard of Sabha Khola B HPP |
Sitalpati S/S |
Survey Lic No: 632 Date: 2080-12-27 till 2082-12-26 |
264 |
Mid Hongu B HPP 132kV Transmission line Project |
132 |
25.79 |
44.9 |
265 |
2081-12-13 |
2106-12-12 |
Gauri Shanker Power Development Ltd |
Naxal |
Respective Switchyard of the project |
Tingla S/S |
Survey Lic No: 656 Date: 2081-05-23;Double ckt;Mid Hongu A (22MW)+Mid Hongu B(22.9) |
265 |
Madhya Super Daraudi - Ghyampesal 33kV Transmission Line Project |
33 |
18.91 |
10 |
266 |
2082-01-10 |
2107-01-09 |
Barpak Daraudi Hydropower Pvt. Ltd. |
Kathmandu |
Switchyard of Project |
NEA Ghyampesal S/S |
Single ckt;Survey Lic No: 641 Date: 2081-02-04, |
266 |
Solar PV Dhalkebar 33kV Transmission Lone Project |
33 |
4.5 |
5 |
267 |
2082-01-22 |
2107-01-21 |
Green Infrastructure Pvt.Ltd |
Babarmahal, Kathmandu |
Respective Switchyard of the project |
NEA-Dhalkebar s/s |
Survey Lic No: 672 Date: 2081-07-25;Single ckt |
267 |
Duhabi Solar Farm 33 kV Transmission Line Project |
33 |
10.42 |
8 |
268 |
2082-01-22 |
2107-01-21 |
Global Energy & Construction Pvt..Ltd |
Naxal, Kathmandu |
Respective Switchyard of the project |
Duhabi s/s |
Survey Lic No: 658 Date: 2081-05-30;Single ckt |
268 |
Nepalgaunj Nanpara 132 kV Transmission Line Project |
132 |
22.53 |
200 |
269 |
2082-02-04 |
2107-02-03 |
Nepal Electricity Authority |
Durbar Marg, Kathmandu 01-4153007 |
NEA New Nepalgaunj |
NEA Old Nepalgunj S/S |
Survey Lic No: 592 Date: 2079-12-20;Doubleckt & multi ckt |
269 |
Upper Tamor Hydropower Project |
220 |
4.7 |
285 |
270 |
2082-02-04 |
2107-02-03 |
Tamor Energy Pvt.Ltd. |
Kupondole,Lalitpur |
Switchyard of Project (Taplejung ) |
Switchyard of Madhya Tamor HPP |
Survey Lic No: 433 Date: 2076-08-25;Double ckt |
270 |
Dhaubadi Meghauli 132 kV Transmission Line Project |
132 |
14.931 |
200 |
271 |
2082-02-06 |
2107-02-05 |
Nepal Electricity Authority |
Durbar Marg, Kathmandu 01-4153007 |
Dhaubadi/Gaidakot |
Meghauli s/s |
Survey Lic No: 581 Date: 2079-10-24; Double ckt |
271 |
Thimi Balkumari 132 kV Underground Transmission Line Project |
132 |
8 |
300 |
272 |
2082-03-01 |
2107-02-30 |
Nepal Electricity Authority |
Durbar Marg, Kathmandu 01-4153007 |
NEA Thimi S/S |
NEA Proposed Balkumari |
Survey Lic No: 550 Date: 2079-02-27;Double ckt |
272 |
Nalgad Maintada (Bheri Corridor) Transmission Line |
400 |
75 |
2400 |
273 |
2082-04-14 |
2107-04-13 |
Rastriya Prasaran Grid Company Limited |
Babarmahal, Kahmandu |
Proposed Nalgad S/S |
Proposed Maintada S/S |
Survey Lic No: 386 Date: 2075-11-26;Double ckt |
273 |
Khorunga Khola Small HEP Transmission Line Project |
33 |
4.38 |
4.8 |
274 |
2082-05-15 |
2107-05-14 |
Reliable Hydro Power Co. Pvt. Ltd. |
Jawalakhel Lalitpur, POB 516; 015551616 |
Switchyard of Project |
NEA Jiri Khimti S/S |
Survey Lic No: 564 Date: 2079-05-28;Single ckt |
274 |
Upper Sardi Khola Hydropower Project |
33 |
3.68 |
2.9 |
275 |
2082-05-18 |
2107-05-17 |
Mandakini Hydropower Ltd. |
Sinamangal-9 Kathmandu |
Swiychyard of Project (Kaski) |
Switchyard of Sardi HPP(4 MW) |
Survey Lic No: 422 Date: 2076-08-10;Single ckt |