NepalFlag

वि.सं:

नेपाल संवत: ११४५ ञलागा तृतीया - १८

थर्मल

Power Plants :: Thermal

Updated on - Jul 07, 2025

S No Project Capacity (MW) Lic No Isuue Date Validity Promoter Address Latitiude N Longitude E VDC/District C O D
1 Hetauda Diesel Centre 14.410 051/52/B.U.P.B. 001 2051-12-06 2101-11-30 Nepal Electricity Authority 00o 00' 00" 00o 00' 00" 00o 00' 00" 00o 00' 00" (Makawanpur)
2 Duhabi Multifuel Center 39.000 051/52/B.U.P.B. 001 2051-12-06 2101-11-30 Nepal Electricity Authority 00o 00' 00" 00o 00' 00" 00o 00' 00" 00o 00' 00" (Morang)

Total capacity for 2 projects = 53.41 MW